China Eximbank provides RMB 1.795 billion government concessional loan for 64MW Ranomafana Hydropower Plant Construction Project

Commitments (Constant USD, 2023)$253,515,175
Commitment Year2023Country of ActivityMadagascarDirect Recipient Country of IncorporationMadagascarSectorEnergyFlow TypeLoan

Status

Project lifecycle

Implementation

Pipeline: PledgePipeline: CommitmentImplementationCompletion

Timeline

Key dates

Commitment date
Aug 1, 2023
Start (actual)
Dec 19, 2024
End (planned)
Jun 1, 2028
First repayment (originally scheduled)
Oct 12, 2027
Last repayment (originally scheduled)
Aug 29, 2054

Geospatial footprint

Map overview

Visualizes the AidData-provided feature geometry for this project.

Loading map…

The project involves the construction of the 64MW Ranomafana hydroelectric power plant on the Ikopa River in Anamalanga, roughly 115 north-west of Antananarivo. The power plant's exact locational coordinates are 18°36’0.63’’S, 47°01'37.85’’E. The project also involves the construction of a 90 km transmission line HT/MT from the dam to Tanà Nord (Antanandano). More detailed locational information can be found at: https://www.openstreetmap.org/way/1085526912

Stakeholders

Organizations involved in projects and activities supported by financial and in-kind transfers from Chinese government and state-owned entities

Ultimate beneficial owners

At least 25% host country ownership

Funding agencies

State-owned Policy Banks

  • Export-Import Bank of China (China Eximbank)

Receiving agencies

Government Agencies

  • Government of Madagascar

Implementing agencies

State-owned companies

  • Sinohydro Corporation Limited

Loan desecription

China Eximbank provides RMB 1.795 billion government concessional loan for 64MW Ranomafana Hydropower Plant Construction Project

Grace period4.2 yearsGrant element64.028%Interest rate (t₀)1.5%Interest typeFixed Interest RateMaturity31.1 years

Narrative

Full Description

Project narrative

In 2016, China Eximbank agreed in principle to provide Madagascar’s Ministry of Water, Energy, and Hydrocarbons (MEH) a concessional loan for the development of the 64MW Ranomafana Hydropower Plant Construction Project. However, the project experienced a number of delays, and as of late 2022, it had still not reached the implementation stage. Then, on April 6, 2023, China Eximbank and the Government of Madagascar signed a preferential loan framework agreement for the 64MW Ranomafana Hydropower Plant Construction Project. On August 1, 2023, China Eximbank and the Government of Madagascar signed a government concessional loan (GCL) agreement worth RMB 1,795,000,000 ($239,337,340) for the 64MW Ranomafana Hydropower Plant Construction Project. The borrowing terms of the loan include a 31.1-year maturity, a 4.2-year grace period, a 1.5% interest rate, nd a 0.5% management fee. The borrower is expected to use the loan proceeds to partially finance a $216 million commercial (EPC) contract with Sinohydro Corporation Limited, which was signed in 2018. The project involves the construction of the 64MW Ranomafana hydroelectric power plant on the Ikopa River in Anamalanga, roughly 115 north-west of Antananarivo. The power plant's exact locational coordinates are 18°36’0.63’’S, 47°01'37.85’’E. The project also involves the construction of a 90 km transmission line HT/MT from the dam to Tanà Nord (Antanandano). Upon completion, the power plant is expect to to generate an average of 311 million kilowatt hours per year. The project is expected to affect 3 regions (Analamanga, Bongolava and Itasy) 5 districts (Ambohidratrimo, Ankazobe, Fenoarivobe, Miarinarivo and Arivonimamo) and 15 municipalities (Ambohidratrimo, Anosiala, Mahitsy, Mananjara, Ampanotokana, Fihaonana, Mahavelona, Ambohitromy, Antotohazo, Miantso, Maritampona, Soavimbazaha, Ambatomanga, Talata Tsimadilo, Ambohimasina). Sinohydro Corporation Limited is the EPC contractor responsible for project implementation. The project officially commenced on December 19, 2024 and the Ranomafana hydroelectric power plant was originally scheduled to be commissioned in June 2028.

Staff comments

1. The French project title is Projet d'aménagement du site hydroélectrique de Ranomafana sur l'Ikopa or la centrale hydroélectrique de Ranomafana or la centrale hydroéléctrique de Ranomafana-Ikopa. 2. The Chinese project title is 马达加斯加哈努马法纳水电站项目 or 哈努马法纳水电站项目 or 及哈努马法那热水电站 or 哈努马法纳水电项目 or 哈努马法纳水电站项目. 3. The loan's borrowing terms were identified via http://www.tresorpublic.mg/tresorpublic/download.php?path=wp-content/themes/tresor-public/statik-content/tresor-public/temp/statistique/bsd/&file=031.pdf