China Eximbank provides RMB 19.4 million loan for Kasane Housing Project (86 Units)

Commitments (Constant USD, 2023)$5,580,883
Commitment Year2000Country of ActivityBotswanaDirect Recipient Country of IncorporationBotswanaSectorOther Social Infrastructure And ServicesFlow TypeLoan

Status

Project lifecycle

Completion

Pipeline: PledgePipeline: CommitmentImplementationCompletion

Timeline

Key dates

Commitment date
Jan 1, 2000
End (actual)
May 31, 2005
First repayment (originally scheduled)
Dec 31, 2003
Last repayment (originally scheduled)
Dec 29, 2011

Geospatial footprint

Map overview

Visualizes the AidData-provided feature geometry for this project.

Loading map…

The purpose of this project was for the China Eximbank loan RMB 19.4 million for the Kasane Housing Project in Botswana. More detailed locational information can be found at: https://www.openstreetmap.org/node/1712387804

Stakeholders

Organizations involved in projects and activities supported by financial and in-kind transfers from Chinese government and state-owned entities

Ultimate beneficial owners

At least 25% host country ownership

Funding agencies

State-owned Policy Banks

  • Export-Import Bank of China (China Eximbank)

Receiving agencies

Government Agencies

  • Government of Botswana

State-owned companies

  • Botswana Housing Corporation

Implementing agencies

State-owned companies

  • Botswana Housing Corporation
  • China Overseas Engineering Group Co., Ltd. (COVEC)
  • Complant Botswana (Ptya) Ltd.

Loan description

China Eximbank provides RMB 19.4 million loan for Kasane Housing Project (86 Units)

Grace period4 yearsGrant element30.7323%Interest rate (t₀)4%Interest typeFixed Interest RateMaturity12 years

Narrative

Full Description

Project narrative

In 2000, China Eximbank and the Government of Botswana signed an RMB 22,557,815 loan agreement for the Kasane Housing Project (86 Units). This loan carried the following borrowing terms: a 12 year maturity, a 4 year grace period, and a 4% interest rate. The face value of the loan was subsequently revised to RMB 19,490,521. The Government of Botswana used the proceeds from the loan to on-lend to the Botswana Housing Corporation (BHC) at a significantly higher interest rate (approximately 8.5%). The BHC, in turn, used the proceeds from its subsidiary loan agreement with the Government of Botswana to construct 86 housing units in the town of Kasane. Complant Botswana (Pty) Ltd., a subsidiary of China National Overseas Engineering Corporation, was the contractor responsible for implementation. This project was completed, but its precise date of completion is unknown.

Staff comments

1. Some sources indicate that this loan was secured in late 1999 and others indicate that it was secured in 2000. 2. There is also disagreement across sources with respect to the final maturity date of the loan. SAIS-CARI records a maturity length of 16 years. Botswana’s Ministry of Finance and Economic Development records a maturity = of 12 years. AidData relies on the maturity that is recorded by Botswana’s Ministry of Finance and Economic Development.