Chinese Government provides RMB 346 million grant for Parliament Building Construction Project

Commitments (Constant USD, 2023)$54,486,222
Commitment Year2017Country of ActivityCongoDirect Recipient Country of IncorporationCongoSectorOther Social Infrastructure And ServicesFlow TypeGrant

Status

Project lifecycle

Completion

Pipeline: PledgePipeline: CommitmentImplementationCompletion

Timeline

Key dates

Commitment date
Feb 26, 2017
Start (actual)
Apr 30, 2017
End (actual)
Mar 3, 2021

Geospatial footprint

Map overview

Visualizes the AidData-provided feature geometry for this project.

Loading map…

The new parliament building is located alongside Boulevard Denis Sassou-Nguesso and Avenue du général De Gaulle in the Plateau-Center-ville district of Brazzaville (across from the Commissariat central de police, the Ministry of Justice, and l’Institut français du Congo). More detailed locational information can be found at https://www.openstreetmap.org/way/731889974.

Stakeholders

Organizations involved in projects and activities supported by financial and in-kind transfers from Chinese government and state-owned entities

Funding agencies

Government Agencies

  • China Ministry of Commerce

Receiving agencies

Government Agencies

  • Government of Republic of Congo

Implementing agencies

State-owned companies

  • Beijing Institute of Architectural Design (BIAD)
  • China Jiangsu Construction Engineering Corporation
  • Shenyang Engineering & Supervision Consulting Co., Ltd. (Shenyang Supervision)

Loan desecription

Chinese Government provides RMB 346 million grant for Parliament Building Construction Project

Narrative

Full Description

Project narrative

In 2017, China’s Ministry of Commerce (MOFCOM) provided an RMB 346 million ($58 million) grant to the Republic of Congo for the Parliament Building Construction Project. This project involved the construction of a new parliament building (Palais du Parlement) in the capital city of Brazzaville. The building comprises of two main sections each containing three levels. One section houses the National Assembly and the other houses the Senate. Each section contains seven meeting rooms with 50 seats each, a press room, two VIP lounges, two permanent and auxiliary committee rooms, technical rooms, restrooms, and a health care room. There are also archive rooms, libraries, and 540 parking spaces. Lastly, the building includes 500 seats for members of the National Assembly and 300 seats for the members of the Congolese Senate. Beijing Institute of Architectural Design and Research Co., Ltd. and Shenyang Engineering Supervision Consulting Co., Ltd. were responsible for project design and supervision. Jiangsu Provincial Construction LTD was the contractor responsible for implementation. It was awarded a MOFCOM contract in December 2016. The project officially commenced on April 30, 2017. On May 22, 2017, Congolese President Sassou Nguesso and a delegation from MOFCOM attended a foundation laying ceremony. Then, on January 12, 2018, the Chinese Ambassador to the Republic of Congo conducted a project site visit. The project was originally expected to reach completion in August 2020. However, due to the COVID-19 pandemic, construction was temporarily suspended. The project was officially handed over on March 3, 2021.

Staff comments

1. The Chinese project title is 援刚果(布)新议会大厦项目 or 援刚新议会大厦项目. The French project title is la construction du nouveau siège du Parlement de Brazzaville.