China Eximbank provides CFA 2.76 billion loan for 128MW Sambangalou Hydroelectric Power Plant Project

Commitments (Constant USD, 2023)$5,052,521
Commitment Year2017Country of ActivitySenegalDirect Recipient Country of IncorporationSenegalSectorEnergyFlow TypeLoan

Status

Project lifecycle

Implementation

Pipeline: PledgePipeline: CommitmentImplementationCompletion

Timeline

Key dates

Commitment date
Jan 1, 2017
Start (actual)
Feb 4, 2017

Geospatial footprint

Map overview

Visualizes the AidData-provided feature geometry for this project.

Loading map…

The Sambangalou hydroelectric power is located in Senegal, 930 km upstream from the mouth of the Gambia River and about 25 km south of Kédougou. This project also involves the construction of 1,677 km of 225 kV power transmission lines. These transmission lines will cut across Senegal’s Tambacounda, Kaolack and Kolda Regions. More detailed locational information can be found at: https://www.openstreetmap.org/way/320679323, https://www.openstreetmap.org/relation/3405109, https://www.openstreetmap.org/relation/3405263, https://www.openstreetmap.org/relation/3405108

Stakeholders

Organizations involved in projects and activities supported by financial and in-kind transfers from Chinese government and state-owned entities

Ultimate beneficial owners

At least 25% host country ownership

Funding agencies

State-owned Policy Banks

  • Export-Import Bank of China (China Eximbank)

Cofinancing agencies

Intergovernmental Organizations

  • African Development Bank (AfDB) (ADB) (BAD)
  • Economic Community of West African States (ECOWAS)
  • European Investment Bank

NGO/CSO/Foundations

  • International Development Association

State-owned Banks

  • French Development Agency (AFD)
  • KfW Development Bank (KfW Entwicklungsbank GmbH)

Receiving agencies

Government Agencies

  • Government of Senegal

Implementing agencies

Government Agencies

  • Government of Senegal

State-owned companies

  • China Gezhouba Group Company Ltd. (CGGC)

Loan desecription

China Eximbank provides CFA 2.76 billion loan for 128MW Sambangalou Hydroelectric Power Plant Project

Interest typeUnknown

Narrative

Full Description

Project narrative

In 2017, China Eximbank and the Government of Senegal signed a loan agreement for the 128MW Sambangalou Hydroelectric Power Plant Project. The exact face value and commitment date of this loan are unknown; however, according to the Government of Senegal’s External Financing Management Platform (la Plateforme de Gestion des Financements Extérieurs du Sénégal, or PGFE), China Eximbank made a loan disbursement for this project worth CFA 2,763,505,191 (or approximately $4,818,666) on December 30, 2017. The total cost of the 128MW Sambangalou Hydroelectric Power Plant Project is $454 million and the Government of Senegal has secured grants and loans worth approximately $129,227,305 (or 74,111,862,534 CFA Francs) for this project from a group of donors and lenders, including ECOWAS, International Development Association (IDA), KFW, European Investment Bank (EIB), China Eximbank, French Development Agency (AFD), and the African Development Bank. The project has two components. The first component involves the construction of an interconnection for the four member countries (Senegal, Guinea Bissau, Guinea Conakry, and the Gambia) in the Senegal River Basin Authority, which is also known as the Organisation pour la mise en valeur du fleuve Sénégal (OMVS). To this end, a 128MW hydroelectric power plant will be installed on the Gambia River and 1,677 km of 225 kV power transmission lines will also be constructed. These transmission lines will cut across Senegal’s Tambacounda, Kaolack and Kolda Regions. The second component project involves the construction of fifteen 225/30kW sub-stations. The overall purpose of the project is to increase the population's access to electricity. China Gezhouba China Group Corporation Limited (CGGC Ltd) is the contractor responsible for implementation. A groundbreaking ceremony was held on February 4, 2017, and the project had achieved a 58% completion rate as of February 2019. The power plant's commercial commissioning was originally scheduled to take place in 2025.

Staff comments

1. This project is also known as the OMVG Energy Project or Gambia River Basin Development Project. The French project title is Barrage de Samba Galou or Project Energie OMVG or Construction de la centrale hydroélectrique OMVG 128 MW de Sambangalou. The Chinese project title is 桑巴加鲁水电站项目 or Sambangalou水电站这 or 桑邦加卢Sambangalou水电站,该水电站装机容量为128 MW. 2. The China Eximbank loan that supported the 128MW Sambangalou Hydroelectric Power Plant Project is omitted from the database of Chinese loan commitments that SAIS-CARI released in July 2020.