China Eximbank provides CFA 2.76 billion loan for 128MW Sambangalou Hydroelectric Power Plant Project
Commitment amount
$ 5471354.532781531
Adjusted commitment amount
$ 5471354.53
Constant 2021 USD
Summary
Funding agency [Type]
Export-Import Bank of China (China Eximbank) [State-owned Policy Bank]
Recipient
Senegal
Sector
Energy (Code: 230)
Flow type
Loan
Level of public liability
Central government debt
Infrastructure
Yes
Category
Project lifecycle
Geography
Description
In 2017, China Eximbank and the Government of Senegal signed a loan agreement for the 128MW Sambangalou Hydroelectric Power Plant Project. The exact face value and commitment date of this loan are unknown; however, according to the Government of Senegal’s External Financing Management Platform (la Plateforme de Gestion des Financements Extérieurs du Sénégal, or PGFE), China Eximbank made a loan disbursement for this project worth CFA 2,763,505,191 (or approximately $4,818,666) on December 30, 2017. The total cost of the 128MW Sambangalou Hydroelectric Power Plant Project is $454 million and the Government of Senegal has secured grants and loans worth approximately $129,227,305 (or 74,111,862,534 CFA Francs) for this project from a group of donors and lenders, including ECOWAS, International Development Association (IDA), KFW, European Investment Bank (EIB), China Eximbank, French Development Agency (AFD), and the African Development Bank. The project has two components. The first component involves the construction of an interconnection for the four member countries (Senegal, Guinea Bissau, Guinea Conakry, and the Gambia) in the Senegal River Basin Authority, which is also known as the Organisation pour la mise en valeur du fleuve Sénégal (OMVS). To this end, a 128MW hydroelectric power plant will be installed on the Gambia River and 1,677 km of 225 kV power transmission lines will also be constructed. These transmission lines will cut across Senegal’s Tambacounda, Kaolack and Kolda Regions. The second component project involves the construction of fifteen 225/30kW sub-stations. The overall purpose of the project is to increase the population's access to electricity. China Gezhouba China Group Corporation Limited (CGGC Ltd) is the contractor responsible for implementation. A groundbreaking ceremony was held on February 4, 2017, and the project had achieved a 58% completion rate as of February 2019. The power plant's commercial commissioning was originally scheduled to take place in 2025.
Additional details
1. This project is also known as the OMVG Energy Project or Gambia River Basin Development Project. The French project title is Barrage de Samba Galou or Project Energie OMVG or Construction de la centrale hydroélectrique OMVG 128 MW de Sambangalou. The Chinese project title is 桑巴加鲁水电站项目 or Sambangalou水电站这 or 桑邦加卢Sambangalou水电站,该水电站装机容量为128 MW. 2. The China Eximbank loan that supported the 128MW Sambangalou Hydroelectric Power Plant Project is omitted from the database of Chinese loan commitments that SAIS-CARI released in July 2020.
Number of official sources
16
Number of total sources
22
Details
Cofinanced
Yes
Cofinancing agencies [Type]
Economic Community of West African States (ECOWAS) [Intergovernmental Organization]
European Investment Bank [Intergovernmental Organization]
French Development Agency [State-owned Bank]
African Development Bank (AfDB) (ADB) (BAD) [Intergovernmental Organization]
Germany Development Bank (KFW) [State-owned Bank]
International Development Association [NGO/CSO/Foundation]
Direct receiving agencies [Type]
Government of Senegal [Government Agency]
Implementing agencies [Type]
Gezhouba Group [State-owned Company]
Government of Senegal [Government Agency]