Skip to content

Overview

Chinese Government provides $7.44 million grant for Mosaka and Sibiti Water Supply Project

Commitments (Constant USD, 2023)$17,279,562
Commitment Year2001Country of ActivityCongoDirect Recipient Country of IncorporationCongoSectorWater Supply And SanitationFlow TypeGrant

Status

Project lifecycle

Completion

Pipeline: PledgePipeline: CommitmentImplementationCompletion

Timeline

Key dates

Commitment date
Jan 1, 2001
Start (actual)
Mar 1, 2004
End (actual)
Jan 1, 2005

Geospatial footprint

Map overview

Visualizes the AidData-provided feature geometry for this project.

Loading map…

This project involved the construction of 7 boreholes and an adduction system (including a 300m³ water tower, an auxiliary service room with an area of 2000m³, and a 20km water supply pipe) in the district of Sibiti and the construction of 3 boreholes and an adduction system (including a 300m³ water tower, an auxiliary service room with an area of 2000m³, and a 20km water supply pipe) in the district of Mosaka. More detailed locational information can be found at: https://www.openstreetmap.org/relation/3220594

Stakeholders

Organizations involved in projects and activities supported by financial and in-kind transfers from Chinese government and state-owned entities

Funding agencies

Government Agencies

  • China Ministry of Commerce

Receiving agencies

Government Agencies

  • Government of Republic of Congo

Implementing agencies

State-owned companies

  • China Geo-Engineering Corporation (CGC)
  • Weihai International Economic & Technical Cooperative Co., Ltd (WIETC)

Loan desecription

Chinese Government provides $7.44 million grant for Mosaka and Sibiti Water Supply Project

Narrative

Full Description

Project narrative

On October 12, 1992 and November 2, 1992, the Chinese Government and the Republic of Congo signed letters of exchange related to the Mosaka and Sibiti Water Supply Project. A project feasibility study was completed in August 1992 and a project design contract was signed on September 29, 1995. Exploration and drilling work were completed in March 1996, and construction designs were drawn up in December 1996. However, due to civil conflict, the funding for and implementation of this project was delayed. Then, on November 16, 2001, additional project preparation work was completed. The final design of the project involved the construction of 7 boreholes and an adduction system (including a 300m³ water tower, an auxiliary service room with an area of 2000m³, and a 20km water supply pipe) in the district of Sibiti (with approximately 20,000 residents) and the construction of 3 boreholes and an adduction system (including a 300m³ water tower, an auxiliary service room with an area of 2000m³, and a 20km water supply pipe) in the district of Mosaka (with approximately 18,000 residents). Upon completion, it was envisaged that the project would deliver 1000m³ to Mosaka and 1500m³ to Sibiti each day. According to the World Bank, the Chinese Government ultimately provided $5.79 million of grant funding for the Sibiti Water Supply Project and $1.65 million of grant funding for the Mosaka Water Supply Project. China Geological Engineering Co., Ltd. was the contractor responsible for project design and Weihai International Economic and Technical Cooperation Co., Ltd. was the contractor responsible for project implementation. Implementation commenced in March 2004 and was completed in January 2005.

Staff comments

Chinese project name is 莫萨卡、锡比提两城市供水工程 or 奥旺多韦索西比蒂和莫萨卡城市供水 or 援刚果(布)两城市供水项目. The French project title is la construction de 7 forages plus système d’adduction à Sibiti et 3 forages plus système d’adduction à Mosaka.