Project ID: 58864

Chinese Government provides RMB 300 million grant — via ETCA — for Jur River Bridge Construction Project

Commitment amount

$ 49086004.621548295

Adjusted commitment amount

$ 49086004.62

Constant 2021 USD

Summary

Funding agency [Type]

China Ministry of Commerce [Government Agency]

Recipient

South Sudan

Sector

Transport and storage (Code: 210)

Flow type

Grant

Infrastructure

Yes

Category

Intent

Development (The next section lists the possible statuses.)

Commercial

Development

Representational

Mixed

Financial Flow Classification

ODA-like (The next section lists the possible statuses.)

Official Development Assistance

Other Official Flows

Vague (Official Finance)

Flows categorized based on OECD-DAC guidelines

Project lifecycle

Status

Implementation (The next section lists the possible statuses.)

Pledge

Commitment

Implementation

Completion

Suspended

Cancelled

Milestones

Commitment

2019-01-01

Planned start

2021-01-31

Actual start

2021-04-14

Planned complete

2023-07-30

NOTE: Red circles denote delays between planned and actual dates

Geography

Description

On April 10, 2019, the Chinese Government and the Government of South Sudan signed an RMB 300 million grant agreement for the Jur River Bridge Construction Project. The grant proceeds were drawn from an Economic and Technical Cooperation Agreement (ECTA) that was previously signed by the parties. A project implementation agreement was then signed on August 28, 2019 and a supplementary project implementation agreement was signed on September 24, 2020. The purpose of the project is to construct a 1,480 meter bridge over the Jur River that is located in Wau City, the second largest city in South Sudan. Upon completion, the bridge will connect Juba to the Bahr El Ghazal region and its northern neighbor Sudan. The new bridge is located 200 meters north of the old Jur River bridge, which developed technical problems. Tianyuan Construction Group Co., Ltd. is the contractor responsible for project implementation. CCCC Highway Planning and Design Institute Co., Ltd. and Beijing CCCC Highway and Bridge Engineering Supervision Co., Ltd. are the contractors responsible for project design and supervision. Construction began on January 31, 2021, and a formal groundbreaking ceremony took place on or around April 19, 2021. It was originally expected that the bridge would be put into use on July 30, 2023.

Additional details

1. This project is known as the Jur River Bridge Project, the Juer River Bridge Project, or the The South Jur River Bridge Project. The Chinese project title is 中国援南苏丹朱尔河大桥项目 or 援南苏丹朱尔河大桥项目 or 南苏丹朱尔河大桥项目 or 援南苏丹朱尔河大桥项目.

Number of official sources

15

Number of total sources

26

Download the dataset

Details

Cofinanced

No

Direct receiving agencies [Type]

Government of South Sudan [Government Agency]

Implementing agencies [Type]

CCCC Highway Consultants Co., Ltd. (中交公路规划设计院有限公司) [State-owned Company]

Tianyuan Construction Group [Private Sector]