Project ID: 59258

China Eximbank provides $35.9 million loan for Dorale-Nagad Railway Ramp Project

Commitment amount

$ 54819170.09490075

Adjusted commitment amount

$ 54819170.09

Constant 2021 USD

Summary

Funding agency [Type]

Export-Import Bank of China (China Eximbank) [State-owned Policy Bank]

Recipient

Djibouti

Sector

Transport and storage (Code: 210)

Flow type

Loan

Level of public liability

Central government debt

Infrastructure

Yes

Category

Intent

Development (The next section lists the possible statuses.)

Commercial

Development

Representational

Mixed

Financial Flow Classification

ODA-like (The next section lists the possible statuses.)

Official Development Assistance

Other Official Flows

Vague (Official Finance)

Flows categorized based on OECD-DAC guidelines

Project lifecycle

Status

Completion (The next section lists the possible statuses.)

Pledge

Commitment

Implementation

Completion

Suspended

Cancelled

Milestones

Commitment

2008-01-01

Actual start

2013-07-07

Actual complete

2017-01-10

Description

On June 20, 2008, China Railway Construction Corporation and Djibouti's Minister of Equipment signed a memorandum of understanding (MOU) for the Dorale-Nagad Railway Ramp Project. Then, on December 7, 2011, China Eximbank and the Government of Djibouti signed a $35,956,760 (DJF 6,398,000,000) concessional loan agreement for the project. The borrowing terms of the loan are unknown. However, it is known that the borrower was expected to use the loan proceeds to finance a commercial contract with China Railway Construction Corporation, which was signed on April 15, 2009. The project involved the construction of a 12 km railway connection line from Dorale New Port to Nagad station in Djibouti. The originally expected duration of the construction period was two years. The project reportedly reached completion, but its precise implementation start and end dates are unknown.

Additional details

1. The French project title is Bretelle de chemin de fer Dorale/Nagad or Liaison du Port de Doraleh à Nagad par une bretelle ferrée or le projet de construction d'un rail reliant Doraleh et Nagad.

Number of official sources

9

Number of total sources

9

Download the dataset

Details

Cofinanced

No

Direct receiving agencies [Type]

Government of Djibouti [Government Agency]

Implementing agencies [Type]

China Railway Construction Corporation (CRCC) [State-owned Company]

Loan Details

Bilateral loan

Investment project loan