Skip to content

Overview

China Eximbank provides $81.4 million buyer's credit loan for Bole-Lemi and Kilinto Industrial Zone Power Transmission Project

Commitments (Constant USD, 2023)$86,621,520
Commitment Year2017Country of ActivityEthiopiaDirect Recipient Country of IncorporationEthiopiaSectorEnergyFlow TypeLoan

Status

Project lifecycle

Implementation

Pipeline: PledgePipeline: CommitmentImplementationCompletion

Timeline

Key dates

Commitment date
Dec 12, 2017
Start (actual)
Sep 9, 2019
First repayment (originally scheduled)
Jul 21, 2024
Last repayment (originally scheduled)
Jan 21, 2034

Geospatial footprint

Map overview

Visualizes the AidData-provided feature geometry for this project.

Loading map…

The purpose of the project was to construct 28.4 km of 400 kV and 230 kV high voltage electricity transmission lines to the Bole and Kilinto Industrial Zones in Addis Ababa, construct a 230/33 kV Kilinto substation, construct a 230/33 kV Bole-Lemi Power substation, construct a 400/230/15 kV Koye Abbo substation, and expand an existing 400 kV Gelan substation. More detailed locational information can be found at: https://www.openstreetmap.org/way/895654714 and https://www.openstreetmap.org/way/744369348 and https://www.openstreetmap.org/way/744369343 and https://www.openstreetmap.org/way/895654713 and https://www.openstreetmap.org/way/890762637 and https://www.openstreetmap.org/way/895654715 and https://www.openstreetmap.org/way/576081254

Stakeholders

Organizations involved in projects and activities supported by financial and in-kind transfers from Chinese government and state-owned entities

Ultimate beneficial owners

At least 25% host country ownership

Funding agencies

State-owned Policy Banks

  • Export-Import Bank of China (China Eximbank)

Receiving agencies

State-owned companies

  • Ethiopian Electric Power Corporation (EEPCo)

Implementing agencies

Private Sector

  • TBEA Co., Ltd.

Guarantors

Government Agencies

  • Government of Ethiopia

Loan desecription

China Eximbank provides $81.4 million buyer's credit loan for Bole-Lemi and Kilinto Industrial Zone Power Transmission Project

Grace period6.613 yearsGrant element7.9854%Interest rate (t₀)8.56%Interest typeFixed Interest RateMaturity16.123 years

Narrative

Full Description

Project narrative

On December 12, 2017, China Eximbank and Ethiopian Electric Power Corporation (EEPCo) — an Ethiopian state-owned power company — signed a $81,401,534.20 (ETB 1,819,025,346) buyer's credit loan agreement for the Bole-Lemi and Kilinto Industrial Zone Power Transmission Project. According to the Government of Ethiopia’s Debt Management and Financial Analysis System (DMFAS), the borrowing terms of the loan include a 16.123-year maturity, a 6.613-year grace period, and a 8.56% interest rate. The loan's first and last scheduled principal payment dates were July 21, 2024 and January 21, 2034, respectively. Its first and last scheduled interest payment dates were January 21, 2020 and July 21, 2033, respectively. The Ethiopian Government issued a sovereign guarantee in support of the loan. The borrower was expected to use the proceeds of the loan to finance 83% of the cost of a $98 million commercial contract between EEPCo and TBEA Co., Ltd., which was signed in April 2016. According to the Government of Ethiopia’s AMP, the ETB 1,819,025,346 loan achieved a 68% disbursement rate, with China Eximbank making a single loan disbursement worth ETB 1,245,292,880 on September 9, 2019. The purpose of the project was to construct 28.4 km of 400 kV and 230 kV high voltage electricity transmission lines to the Bole and Kilinto Industrial Zones in Addis Ababa, construct a 230/33 kV Kilinto substation, construct a 230/33 kV Bole-Lemi Power substation, construct a 400/230/15 kV Koye Abbo substation, and expand an existing 400 kV Gelan substation. TBEA Co., Ltd. is the EPC contractor responsible for implementation. Kilinto, Bole-Lemi, and Koye Abbo substation commissioning and testing activities began in December 2019 and the project was 'fully operationalized' in 2020. However, the project encountered major implementation problems. In June 2020, an electricity transmission tower collapsed after burglars attempted to steal equipment from it, leaving 22 companies operating in Bole-Lemi Industrial Park without electricity. There are also indications that the China Eximbank loan for the Bole-Lemi and Kilinto Industrial Zone Power Transmission Project financially underperformed vis-a-vis the original expectations of the lender. According to the Government of Ethiopia’s Aid Management Platform, as of September 2019, ICBC suspended about $67 million worth of loan disbursements 'due to [the] cross-default situation of the country’ (see Record ID#58616). Then, in August 2021, China Eximbank withheld $339 million loan disbursements for 12 projects (including the Bole-Lemi and Kilinto Industrial Zone Power Transmission Project) and halted project implementation due to Government of Ethiopia’s rapidly dwindling foreign exchange reserves and debt sustainability challenges. Demisu Lemma, the Director of Chinese Cooperation at the Ethiopian Ministry of Finance, noted at the time that the Ethiopian Government was in discussions with China Eximbank about a potential debt rescheduling (that would involved a 5-year maturity extension and a 1-year grace period extension). Then, after considerable delay, the G20 Common Framework (CF) creditor committee for Ethiopia convened in September 2021, with the French Government and the Chinese Government serving as co-chairs. The CF debt rescheduling talks were still ongoing in mid-2023.

Staff comments

1. This project is also known as the Bole-Lemi and Kilinto Industry Zone Power Transmission Project and the Akaki–Koye Abbo-Klinto-Bole-Lemi High Voltage Transmission Line and Substations Project. The Chinese project title is Bole Lemi和Kilinto两个工业园供电项目. 2. The AMP system identification number for the project is 87143436115038. The AMP identifies December 6, 2016 rather than December 12, 2017 as the loan commitment date. This issue warrants further investigation. 3. For the time being, AidData relies on the first loan disbursement date (September 9, 2019) as a proxy for the project implementation start date. This issue warrants further investigation. 4. Demisu (Demissu) Lemma, the Director of Chinese Cooperation at the Ethiopian Ministry of Finance, can be reached at demissulemma1958@gmail.com. 5. The loan identification number in the Government of Ethiopia’s Debt Management and Financial Analysis System (DMFAS) is 20965000 and the corresponding project name in DMFAS is ‘BOLE-LEMI & KILINTO INDUST. ZO’. See https://www.dropbox.com/scl/fi/7nrczfanixvivmiyzqx3i/MOFED-Loan-Level-Data-on-Borrowing-Terms-and-Loan-Performance-September-2024_OTHER_PUBLIC.xlsx?rlkey=5sqhh9ii4t3x8cmz0jf6s7cod&dl=0