Project ID: 59738

Chinese Government provides RMB 73 million grant for Cotonou Congress Center Rehabilitation Project (Linked to Project ID#72541, #72542)

Commitment amount

$ 12448590.794849306

Adjusted commitment amount

$ 12448590.79

Constant 2021 USD

Summary

Funding agency [Type]

China Ministry of Commerce [Government Agency]

Recipient

Benin

Sector

Government and civil society (Code: 150)

Flow type

Grant

Infrastructure

Yes

Category

Intent

Development (The next section lists the possible statuses.)

Commercial

Development

Representational

Mixed

Financial Flow Classification

ODA-like (The next section lists the possible statuses.)

Official Development Assistance

Other Official Flows

Vague (Official Finance)

Flows categorized based on OECD-DAC guidelines

Project lifecycle

Status

Completion (The next section lists the possible statuses.)

Pledge

Commitment

Implementation

Completion

Suspended

Cancelled

Milestones

Commitment

2017-01-01

Planned start

2017-12-01

Actual start

2017-12-19

Planned complete

2019-02-28

Actual complete

2019-06-19

NOTE: Red circles denote delays between planned and actual dates

Geography

Description

In 2017, China’s Ministry of Commerce provided an RMB 73 million grant to the Government of Benin for the Cotonou Congress Center Rehabilitation Project. This project involved a set of renovations to the Cotonou Congress Center, which was originally constructed with interest-free loans from the Chinese Government (as captured via ProjectID#72542 and #72541). More specifically, it involved bathroom renovations, improvements to lighting, sound, and HD project systems, renovations of the red and blue halls, and wall decorations. Beijing Urban Construction Group Co., Ltd., China Railway Engineering Design Consulting Group Co., Ltd., and the Guangdong Guangxin Construction Engineering Supervision Co., Ltd. were the contractors responsible for project design and implementation. This project was implemented between December 19, 2017 and June 19, 2019. It was originally expected to reach completion in February 2019. An official project handover ceremony took place on January 14, 2020.

Additional details

1. The Chinese project title is 贝宁会议大厦维修项目. The French project title is La Rénovation du Palais des Congrès or La Réhabilitation du Palais des Congrès.

Number of official sources

11

Number of total sources

16

Download the dataset

Details

Cofinanced

No

Direct receiving agencies [Type]

Government of Benin [Government Agency]

Implementing agencies [Type]

Beijing Urban Construction Group Co., Ltd. [State-owned Company]

Guangdong Guangxin Construction Engineering Supervision Co., Ltd. [Private Sector]

China Railway Engineering Corporation (CRECG) [State-owned Company]