Project ID: 59742

China Eximbank provides $152.6 million buyer’s credit for Lot 2 of Oil Roads Upgrading Project (Linked to Project ID#59741,#59743)

Commitment amount

$ 170437997.40759438

Adjusted commitment amount

$ 170437997.41

Constant 2021 USD

Summary

Funding agency [Type]

Export-Import Bank of China (China Eximbank) [State-owned Policy Bank]

Recipient

Uganda

Sector

Transport and storage (Code: 210)

Flow type

Loan

Level of public liability

Central government debt

Infrastructure

Yes

Category

Intent

Mixed (The next section lists the possible statuses.)

Commercial

Development

Representational

Mixed

Financial Flow Classification

OOF-like (The next section lists the possible statuses.)

Official Development Assistance

Other Official Flows

Vague (Official Finance)

Flows categorized based on OECD-DAC guidelines

Project lifecycle

Status

Implementation (The next section lists the possible statuses.)

Pledge

Commitment

Implementation

Completion

Suspended

Cancelled

Milestones

Commitment

2020-03-18

Actual start

2018-04-16

Planned complete

2021-04-16

Description

On March 18, 2020, China Eximbank and the Government of Uganda signed a $152,607,763.75 buyer’s credit loan (BCL) agreement (Contract ID#1420113022020210694) for Lot 2 of the Oil Roads Upgrading Project (also known as the 111 km Hoima-Butiaba-Wanseko Road Upgrading Project). The BCL carries the following borrowing terms: a 15-year maturity, 4-year grace period, an annual interest rate of 6-month LIBOR plus 300 basis points (a 3% margin), a default (penalty) interest rate of 1%, a 0.5% management fee ($763,038.82), and a 0.5% commitment fee. The BCL is also supported by a Sinosure credit insurance policy. Then, on June 12, 2020. China Eximbank’s Sovereign Business Department issued a letter to the Government of Uganda’s Ministry of Finance, Planning, and Economic Development, notifying it that ‘all the conditions as set out in Article 16 of the [BCL] agreement have been satisfied’ and the ‘[BCL] agreement becomes effective on and from the date June 12, 2020.’ The borrower is to use the BCL proceeds to finance 85% of the cost of a $179,538,545.59 commercial (EPC) contract (No. UNRA/WORKS/2016-17/00110/02) between the Uganda National Roads Authority (the ‘project owner’) and Chongqing International Construction Corporation, which was signed on January 18, 2018. The borrower and/or the project owner are responsible for paying 15% of the commercial contract amount ($26,930,781.84) with their own funds. According to the Government of Uganda’s Aid Management Platform (AMP), this loan achieved a 90% disbursement rate, with China Eximbank making 10 loan disbursements (worth $137,422,989.95) between 2020 and 2022: a $37,877,042.67 disbursement on September 29, 2020, a $17,377,354.10 disbursement on December 14, 2020, a $11,030,412.57 disbursement on March 30, 2021, a $11,056,870.26 disbursement on May 31, 2021, a $9,413,906.40 disbursement on October 12, 2021, a $17,738,745.02 disbursement on February 22, 2022, a $9,642,914.05 disbursement on June 17, 2022, a $11,791,820.26 disbursement on August 18, 2022, a $5,372,385.06 disbursement on December 13, 2022, and a $6,121,539.56 disbursement on December 26, 2022. According to the Uganda Ministry of Finance, Planning, and Economic Development's Report on Public Debt, Grants, Guarantees and Other Financial Liabilities for Financial Year 2021/2022, as of December 31, 2021, total loan disbursements amounted to $86,755,586 and the loan’s amount outstanding (including arrears) was $86,755,586. The purpose of the project is to upgrade the 111 km Hoima-Butiaba-Wanseko road from gravel to bituminous standard. The main objectives of the project are to: (a) improve the road infrastructure within the mineral and oil exploration zones which are in both Hoima and Bulisa districts; (b) improve access to social and economic development opportunities along the route and integration to the rest of the rest of the country by providing high capacity infrastructure; and (c) ensure that no road side communities become worse off as a result of the road upgrading work. Chongqing International Construction Corporation is the EPC contractor responsible for implementation. Project implementation commenced on April 16, 2018 and the project was originally expected to reach completion on April 16, 2021. However, the project has encountered various implementation delays. As of December 31, 2020, the project had achieved a 71.96% physical progress rate (against a target of 87.88%). As of November 1, 2021, the project had achieved a 90% physical progress rate. Project implementation obstacles have included (i) a delay in the signing of the loan agreement, which led to delayed contractor payments between July 2019 and July 2020; (ii) rising water levels in Lake Albert and River Nile, which resulted in flooding of the northern bank and other implementation problems; (iii) the COVID-19 pandemic, which slowed the pace of construction; (iv) inadequate funds and management of land acquisition problems; and (v) poor planning and coordination by the general contractor and subcontractors.

Additional details

1. This project is also known as the Critical Oil Road Package 2 Project, the Upgrading of Hoima-Butiaba-Wanseko Road (111 km) to Paved Standard Project, the 111km Hoima-Butiaba-Wanseko Road Upgrading Project, and the Civil works for Upgrading of Hoima-Butiaba- Wanseko road from gravel to paved (Bituminous Standard 111km). 2. The buyer’s credit loan agreement (Contract ID#1420113022020210694) is accessible in its entirety via https://www.dropbox.com/s/27soybgikbzuf8f/Upgrading%20of%20Hoima-Butiaba-Wanseko%20Road.pdf?dl=0. 3. The all-in interest rate was calculated by adding 3% to the average 6-month LIBOR rate in March 2020 (0.964%). 4. The Government of Uganda’s internal loan identification number for this China Eximbank BCL is DMFAS No: 201914000. The Government of Uganda’s agreement code for the BCL agreement is L-0758. The system identification number in the Government of Uganda’s Aid Management Platform (AMP) is 872993114183. 5. The June 12, 2020 letter from China Eximbank’s Sovereign Business Department can be accessed in its entirety via https://www.dropbox.com/s/rgi60u2xtwfljyn/Notice%20of%20Effectiveness-Oil%20road%20lot2.pdf?dl=0. 6. This project has a 12-month defects liability period. 7. China Eximbank also issued BCLs for Lot 1 of the Oil Roads Upgrading Project (captured via Project ID#59741) and Lot 3 of the Oil Roads Upgrading Project (captured via Project ID#59743).

Number of official sources

14

Number of total sources

26

Download the dataset

Details

Cofinanced

No

Direct receiving agencies [Type]

Government of Uganda [Government Agency]

Implementing agencies [Type]

Uganda National Roads Authority (UNRA) [Government Agency]

China Chongqing International Construction Corporation (CICO) [State-owned Company]

Insurance provider [Type]

China Export & Credit Insurance Corporation (Sinosure) [State-owned Company]

Loan Details

Maturity

15 years

Interest rate

3.964%

Grace period

4 years

Grant element (OECD Grant-Equiv)

29.7339%

Bilateral loan

Export buyer's credit

Investment project loan