Skip to content

Overview

China Eximbank provides $285.9 million preferential buyer’s credit for 112MW Gribo Popoli Hydropower Plant Construction Project

Commitments (Constant USD, 2023)$296,790,516
Commitment Year2019Country of ActivityCote d'IvoireDirect Recipient Country of IncorporationCote d'IvoireSectorEnergyFlow TypeLoan

Status

Project lifecycle

Implementation

Pipeline: PledgePipeline: CommitmentImplementationCompletion

Timeline

Key dates

Commitment date
Oct 9, 2019
Start (planned)
Oct 1, 2017
Start (actual)
Jan 1, 2018
End (planned)
May 1, 2021
First repayment
Oct 31, 2025
Last repayment
Aug 17, 2036

Geospatial footprint

Map overview

Visualizes the AidData-provided feature geometry for this project.

Loading map…

The purpose of the project is to construct a 112 MW hydroelectric power plant in Gribo Popoli on the Sassandra River (downstream from Buyo and the Soubré dam site). More detailed locational information can be found at https://www.openstreetmap.org/way/1043106265

Stakeholders

Organizations involved in projects and activities supported by financial and in-kind transfers from Chinese government and state-owned entities

Ultimate beneficial owners

At least 25% host country ownership

Funding agencies

State-owned Policy Banks

  • Export-Import Bank of China (China Eximbank)

Receiving agencies

Government Agencies

  • Cote d'Ivoire Ministry of Economy and Finance
  • Cote d'Ivoire Ministry of Petroleum, Energy and New Energy Development
  • Cote d'Ivoire Ministry of State Affairs
  • Government of Cote d'Ivoire

Implementing agencies

State-owned companies

  • Sinohydro Corporation Limited
  • Société des Energies de Côte d’Ivoire (CI-ENERGIES)

Loan desecription

China Eximbank provides $285.9 million preferential buyer’s credit for 112MW Gribo Popoli Hydropower Plant Construction Project

Grace period6.0659 yearsGrant element50.4764%Interest rate (t₀)2.1622%Interest typeFixed Interest RateMaturity16.8699 years

Narrative

Full Description

Project narrative

In October 2015, the Chinese Government and the Government of Cote d'Ivoire discussed the possibility of working together to implement the 112MW Gribo Popoli Hydropower Plant Construction Project. Then, on October 9, 2019, China Eximbank and the Government of Cote d'Ivoire signed a $285,928,798.53 (CFA 171,557,279,118) preferential buyer’s credit (PBC) agreement [CHINA EXIMBANK PBC NO. (2019) 11 TOTAL NO. (494)] for the 112MW Gribo Popoli Hydropower Plant Construction Project. The PBC agreement was ratified by the Ivorian Government on January 8, 2020. It entered into force on March 9, 2020. The borrowing terms of the PBC are unknown. However, it is known that the borrower is expected to use the proceeds of the PBC to finance 85% of the cost of a $336,386,821.80 commercial contract (including a $30.5806 million risk deposit) between the Government of Cote d'Ivoire and SinoHydro 5th Bureau, which was signed in November 2017. The Government of Cote d'Ivoire is also responsible for directly financing 15% ($50,458,023.27) of the commercial contract cost. According to the Government of Cote d'Ivoire's Aid Management Platform (AMP), the China Eximbank loan had achieved a 80.6% disbursement rate (CFA 138,376,607,559.86 out of CFA 171,557,279,118) as of December 31, 2023. 12 China Eximbank loan disbursements (worth CFA 138,376,607,559.86) were made between 2021 and 2032: a CFA 28,025,899,865 disbursement on July 31, 2021, and a CFA 15,963,581,178.86 disbursement on December 31, 2021, a CFA 14,016,023,361 disbursement on March 31, 2022, a CFA 6,297,699,749 disbursement on June 30, 2022, a CFA 12,963,496,194 disbursement on August 31, 2022, a CFA 13,193,693,537 disbursement on December 31, 2022, a CFA 18,749,338,934 disbursement on March 31, 2023, a CFA 10,234,049,498 disbursement on May 31, 2023, a CFA 3,664,540,585 disbursement on June 30, 2023, a CFA 3,746,302,401 disbursement on July 31, 2023, a CFA 3,493,984,615 disbursement on August 31, 2023, and a CFA 8,027,997,642 disbursement on December 31, 2023. The purpose of the project is to construct a 112.3 MW hydroelectric power plant in Gribo Popoli on the Sassandra River (downstream from Buyo dam site and the Soubré dam site) and 10 km of transmission lines. The project also has a ‘project management’ component, involving an Environmental and Social Impact Assessment (ESIA), a Resettlement Action Plant (RAP) and an Environmental and Social Management Plan (ESMP). Upon completion, the power plant is expected to generate 580 gigawatt hours of electricity output. SinoHydro 5th Bureau is the EPC contractor responsible for implementation. A formal groundbreaking ceremony took place on November 2, 2017. However, construction of the access road to the project site did not begin until January 2018. Several months later, in March 2018, construction of the diversion cofferdam and site facilities commenced. The ESIA was launched in May 2018, and the first compensation payments to displaced households were also made during calendar year 2018. The Government of Cote d'Ivoire issued an advance payment to SinoHydro 5th Bureau in May 2020. However, it was not until October 11, 2021 that the construction team began to assemble the power plant and the dam. Construction of the power plant and the dam began on October 27, 2021. On March 9, 2023, the overflow spillway was completed 100 days ahead of schedule. Then, on March 14, 2023, flow closure of the cofferdam took place. Dam impoundment took place on March 2, 2024. Project implementation is running behind schedule. The project was originally expected to reach completion within 40 months (estimated end date: May 2021). According to the Government of Côte d'Ivoire’s Aid Management Platform (AMP), the borrowing institution was delayed in its (advance) payment of $50,458,023.27 to the EPC contractor. Another source of delay was the Government of Côte d'Ivoire’s request (through the Ministry of Finance and Economy or MEF) for an amendment whereby the lender would provide disbursements in proportion to the project’s completion rate (progress).

Staff comments

1. This project is also known as the 112 MW Gribo Popoli Hydroelectric Dam Project. The French project title is Barrage hydroelectrique de Gribo Popoli or projet d’aménagement hydroélectrique de Gribo-Popoli or CONSTRUCTION ET EXPLOITATION DU BARRAGE HYDROELECTRIQUE DE GRIBO POPOLI (112 MW). The Chinese project title is 格西波-波波里水电站 or 公司科特迪瓦格西波波波里水电站项目. 2. The AMP system identification number for the loan is 1120071334029. The AMP project code is 78043500042. 3. The AMP identifies the face value of the loan as CFA 171,557,279,118, which is slightly higher than the figures provided by other official sources. This issue warrants further investigation. 4. The project coordinator is BALET Maxime. 5. According to the World Bank's Debtor Reporting System (DRS), the weighted average grace period of all official sector lending from all Chinese creditors to government and government-guaranteed borrowing institutions in Côte d'Ivoire was 6.0659 years in 2019. AidData estimates the grace period of the Export-Import Bank of China loan that supported the 112MW Gribo Popoli Hydropower Plant Construction Project by using this figure. See https://www.dropbox.com/scl/fi/i7f56vi0ix8drznpbaczg/Weighted-average-borrowing-terms-from-Chinese-Lenders-to-Ivory-Coast-April-2024-IDS-Data-Extraction.xlsx?rlkey=0uj6y8don6vdg39v28f1y4nwz&dl=0 6. According to the World Bank's Debtor Reporting System (DRS), the weighted average maturity of all official sector lending from all Chinese creditors to government and government-guaranteed borrowing institutions in Côte d'Ivoire was 16.8699 years in 2019. AidData estimates the maturity of the Export-Import Bank of China loan that supported the 112MW Gribo Popoli Hydropower Plant Construction Project by using this figure. See https://www.dropbox.com/scl/fi/i7f56vi0ix8drznpbaczg/Weighted-average-borrowing-terms-from-Chinese-Lenders-to-Ivory-Coast-April-2024-IDS-Data-Extraction.xlsx?rlkey=0uj6y8don6vdg39v28f1y4nwz&dl=0 7. According to the World Bank's Debtor Reporting System (DRS), the weighted average interest rate of all official sector lending from all Chinese creditors to government and government-guaranteed borrowing institutions in Côte d'Ivoire was 2.1622% in 2019. AidData estimates the interest rate of the Export-Import Bank of China loan that supported the 112MW Gribo Popoli Hydropower Plant Construction Project by using this figure. See https://www.dropbox.com/scl/fi/i7f56vi0ix8drznpbaczg/Weighted-average-borrowing-terms-from-Chinese-Lenders-to-Ivory-Coast-April-2024-IDS-Data-Extraction.xlsx?rlkey=0uj6y8don6vdg39v28f1y4nwz&dl=0