Project ID: 59809

China Eximbank provides $285.9 million preferential buyer’s credit for 112MW Gribo Popoli Hydropower Plant Construction Project

Commitment amount

$ 321259479.65493876

Adjusted commitment amount

$ 321259479.65

Constant 2021 USD

Summary

Funding agency [Type]

Export-Import Bank of China (China Eximbank) [State-owned Policy Bank]

Recipient

Cote d'Ivoire

Sector

Energy (Code: 230)

Flow type

Loan

Level of public liability

Central government debt

Infrastructure

Yes

Category

Intent

Mixed (The next section lists the possible statuses.)

Commercial

Development

Representational

Mixed

Financial Flow Classification

OOF-like (The next section lists the possible statuses.)

Official Development Assistance

Other Official Flows

Vague (Official Finance)

Flows categorized based on OECD-DAC guidelines

Project lifecycle

Status

Implementation (The next section lists the possible statuses.)

Pledge

Commitment

Implementation

Completion

Suspended

Cancelled

Milestones

Commitment

2019-10-09

Planned start

2017-10-01

Actual start

2018-01-01

Planned complete

2021-05-01

NOTE: Red circles denote delays between planned and actual dates

Geography

Description

In October 2015, the Chinese Government and the Government of Cote d'Ivoire discussed the possibility of working together to implement the 112MW Gribo Popoli Hydropower Plant Construction Project. Then, on October 9, 2019, China Eximbank and the Government of Cote d'Ivoire signed a $285,928,798.53 (CFA 171,557,279,118) preferential buyer’s credit (PBC) agreement [CHINA EXIMBANK PBC NO. (2019) 11 TOTAL NO. (494)] for the 112MW Gribo Popoli Hydropower Plant Construction Project. The PBC agreement was ratified by the Ivorian Government on January 8, 2020. It entered into force on March 9, 2020. The borrowing terms of the PBC are unknown. However, it is known that the borrower is expected to use the proceeds of the PBC to finance 85% of the cost of a $336,386,821.80 commercial contract between the Government of Cote d'Ivoire and SinoHydro 5th Bureau, which was signed in November 2017. The Government of Cote d'Ivoire is also responsible for directly financing 15% ($50,458,023.27) of the commercial contract cost. According to the Government of Cote d'Ivoire's Aid Management Platform (AMP), the China Eximbank loan had achieved a 52.7% disbursement rate (CFA 90,460,393,884.86 out of CFA 171,557,279,118) as of December 31, 2022. 6 China Eximbank loan disbursements (worth CFA 90,460,393,884.86) were made between 2021 and 2022: a CFA 28,025,899,865 disbursement on July 31, 2021, and a CFA 15,963,581,178.86 disbursement on December 31, 2021, a CFA 14,016,023,361 disbursement on March 31, 2022, a CFA 6,297,699,749 disbursement on June 30, 2022, a CFA 12,963,496,194 disbursement on August 31, 2022, and a CFA 13,193,693,537 on December 31, 2022. The purpose of the project is to construct a 112.3 MW hydroelectric power plant in Gribo Popoli on the Sassandra River (downstream from Buyo dam site and the Soubré dam site) and 10 km of transmission lines. The project also has a ‘project management’ component, involving an Environmental and Social Impact Assessment (ESIA), a Resettlement Action Plant (RAP) and an Environmental and Social Management Plan (ESMP). Upon completion, the power plant is expected to generate 580 gigawatt hours of electricity output. SinoHydro 5th Bureau is the EPC contractor responsible for implementation. A formal groundbreaking ceremony took place on November 2, 2017. However, construction of the access road to the project site did not begin until January 2018. Several months later, in March 2018, construction of the diversion cofferdam and site facilities commenced. The ESIA was launched in May 2018, and the first compensation payments to displaced households were also made during calendar year 2018. The Government of Cote d'Ivoire issued an advance payment to SinoHydro 5th Bureau in May 2020. However, it was not until October 11, 2021 that the construction team began to assemble the power plant and the dam. Construction of the power plant and the dam began on October 27, 2021. Project implementation is running behind schedule. The project was originally expected to reach completion within 40 months (estimated end date: May 2021). According to the Government of Côte d'Ivoire’s Aid Management Platform (AMP), the borrowing institution was delayed in its (advance) payment of $50,458,023.27 to the EPC contractor. Another source of delay was the Government of Côte d'Ivoire’s request (through the Ministry of Finance and Economy or MEF) for an amendment whereby the lender would provide disbursements in proportion to the project’s completion rate (progress).

Additional details

1. This project is also known as the 112 MW Gribo Popoli Hydroelectric Dam Project. The French project title is Barrage hydroelectrique de Gribo Popoli or projet d’aménagement hydroélectrique de Gribo-Popoli or CONSTRUCTION ET EXPLOITATION DU BARRAGE HYDROELECTRIQUE DE GRIBO POPOLI (112 MW). The Chinese project title is 格西波-波波里水电站 or 公司科特迪瓦格西波波波里水电站项目. 2. The AMP system identification number for the loan is 1120071334029. The AMP project code is 78043500042. 3. The AMP identifies the face value of the loan as CFA 171,557,279,118, which is slightly higher than the figures provided by other official sources. This issue warrants further investigation. 4. The project coordinator is BALET Maxime.

Number of official sources

10

Number of total sources

27

Download the dataset

Details

Cofinanced

No

Direct receiving agencies [Type]

Cote d'Ivoire Ministry of Petroleum, Energy and New Energy Development [Government Agency]

Cote d'Ivoire Ministry of Economics and Finance [Government Agency]

Cote d'Ivoire Ministry of State Affairs [Government Agency]

Government of Cote d'Ivoire [Government Agency]

Implementing agencies [Type]

SinoHydro [State-owned Company]

Société des Energies de Côte d’Ivoire (CI-ENERGIES) [State-owned Company]

Loan Details

Bilateral loan

Export buyer's credit

Investment project loan

Preferential Buyer's Credit