China Eximbank provides $237.8 million preferential buyer’s credit for Jenelata Dam Construction Project

Commitments (Constant USD, 2023)$237,862,000
Commitment Year2023Country of ActivityIndonesiaDirect Recipient Country of IncorporationIndonesiaSectorEnergyFlow TypeLoan

Status

Project lifecycle

Implementation

Pipeline: PledgePipeline: CommitmentImplementationCompletion

Timeline

Key dates

Commitment date
Sep 6, 2023
Start (planned)
Nov 1, 2023
End (planned)
Jul 1, 2028
First repayment
Jun 23, 2030
Last repayment
Dec 20, 2039

Stakeholders

Organizations involved in projects and activities supported by financial and in-kind transfers from Chinese government and state-owned entities

Ultimate beneficial owners

At least 25% host country ownership

Funding agencies

State-owned Policy Banks

  • Export-Import Bank of China (China Eximbank)

Receiving agencies

Government Agencies

  • Government of Indonesia

Implementing agencies

State-owned companies

  • China CAMC Engineering Co., Ltd. (CAMCE)

Loan desecription

China Eximbank provides $237.8 million preferential buyer’s credit for Jenelata Dam Construction Project

Grace period6.8 yearsGrant element45.3501%Interest rate (t₀)3%Interest typeFixed Interest RateMaturity16.3 years

Narrative

Full Description

Project narrative

In 2016, the Chinese Government reportedly signaled interest in issuing a loan for the construction of Jenelata Dam. Then, on May 7, 2018, the China International Development Cooperation Agency (CIDCA) and the Ministry of Public Works and People's Housing (PUPR) of Indonesia signed letters of exchange for the design of the Jenelata Dam Construction Project. On September 6, 2023, China Eximbank and the Government of Indonesia signed a $237,862,000 preferential buyer’s credit (PBC) agreement for the Jenelata Dam Construction Project. The borrowing terms of the loan include a 16.3-year maturity, a 6.8-year grace period, and a 3% interest rate. The borrower is expected to use the proceeds of the loan to partially finance a $290 million commercial contract between China CAMC Engineering Co Ltd (CAMCE) and the Ministry of Public Works and Housing of Indonesia, which was signed on June 29, 2022. The purpose of the project is to construct a 1,525-meter-long and 62.8-meter-high dam (known as ‘Jenelata Dam’) in Manyampa Village within Gowa District and South Sulawesi Province, creating a reservoir with a capacity of 285 million cubic meters with capacity to to irrigate 24,400 hectares of soil. The dam's expected benefits include not only improved agricultural irrigation but also enhanced flood prevention. CAMCE is the EPC contractor responsible for implementation. On November 1, 2023, it received advance payment from the project owner, which officially started construction. Then, on December 19, 2023, a formal groundbreaking ceremony took place. The project was originally scheduled to reach completion within 56 months (July 1, 2028). As of July 2024, the project was still expected to be completed in 2028.

Staff comments

1. The Chinese project title is 印尼杰那拉塔大坝建设项目 or 杰纳拉塔水坝工程. 2. The loan's borrowing terms are drawn from the World Bank's Debtor Reporting System (DRS). See https://www.dropbox.com/scl/fi/stbsondlzk05t09z7xf7z/Indonesia-s-official-sector-PRC-borrowings-and-borrowing-terms-IDS-December-2024.xlsx?rlkey=9ndf1pbfb7b5le5j55po2i69x&dl=0