China Eximbank provides $48.663 million preferential buyer's credit for Passenger Carriage Manufacturing Plant Project (Linked to Record ID#96221, 98029)

Commitments (Constant USD, 2023)$50,316,145
Commitment Year2013Country of ActivityMyanmarDirect Recipient Country of IncorporationMyanmarSectorTransport And StorageFlow TypeLoan

Status

Project lifecycle

Completion

Pipeline: PledgePipeline: CommitmentImplementationCompletion

Timeline

Key dates

Commitment date
Oct 18, 2013
Start (actual)
Jun 1, 2015
End (actual)
Dec 29, 2018
First repayment (originally scheduled)
Dec 31, 2017
Last repayment (originally scheduled)
Dec 27, 2032

Geospatial footprint

Map overview

Visualizes the AidData-provided feature geometry for this project.

Loading map…

The purpose of this project was to build a passenger carriage manufacturing plant in the town of Myitnge within Mandalay Region. More detailed locational information can be found at: https://www.openstreetmap.org/node/4820843879

Stakeholders

Organizations involved in projects and activities supported by financial and in-kind transfers from Chinese government and state-owned entities

Ultimate beneficial owners

At least 25% host country ownership

Funding agencies

State-owned Policy Banks

  • Export-Import Bank of China (China Eximbank)

Receiving agencies

Government Agencies

  • Myanmar Central Bank

State-owned companies

  • Myanmar Railways

Implementing agencies

State-owned companies

  • China National Machinery Import & Export Corporation (CMC)
  • CRRC Qingdao Sifang Co., Ltd.

Loan desecription

China Eximbank provides $48.663 million preferential buyer's credit for Passenger Carriage Manufacturing Plant Project

Grace period5 yearsGrant element53.1012%Interest rate (t₀)2%Interest typeFixed Interest RateMaturity20 years

Narrative

Full Description

Project narrative

On October 18, 2013, China Eximbank and Myanmar Railways — a state-owned railway company under the Ministry of Rail Transportation — signed a $48.663 million preferential buyer’s credit (PBC) agreement for the Passenger Carriage Manufacturing Plant Project. The PBC carried the following borrowing terms: a 20 year maturity, a 5 year grace period, a 2% interest rate, a 0.25% commitment fee, and a 0.25% management fee. The proceeds of the PBC were to be used by the borrowing to finance 90% of the cost of a $54.070 million EPC contract between Myanmar Railway and China National Machinery Import and Export Corporation, which was signed on July 19, 2013. The purpose of this project was to build a passenger carriage manufacturing plant in the town of Myitnge within Mandalay Region. Upon completion, it was expected that the plant would be able to produce 120 passenger carriages each year. China National Machinery Import and Export Corporation was the general EPC contractor responsible for implementation. CSR Sifang Locomotive and Rolling Stock Corporation Limited was also involved in implementation of the project (most likely as a subcontractor). Construction began on June 1, 2015 and the project was officially completed on December 29, 2018. There are some indications that the China Eximbank loan for the Passenger Carriage Manufacturing Plant Project may have financially underperformed vis-a-vis the original expectations of the lender. In 2020, China Eximbank and the Government of Myanmar signed a debt suspension agreement as part of the G-20 Debt Service Suspension Initiative (DSSI). Under the terms of the agreement, the lender agreed to suspend principal and interest payments due between May 1, 2020 and December 31, 2020 under 3 buyer’s credit loan (BCL) agreements, 6 government concessional loan (GCL) agreements, and 27 preferential buyer’s credit (PBC) agreements (as captured via Record ID#98029). Debt service payments under many of these loan agreements were again deferred in 2021 (as captured via Record ID#96221).

Staff comments

1. This project is also known as the Carriage Construction Plant and Carriage Component Assemblies Project and the Myitnge Train Carriage Factory Project. The Chinese project title is 缅甸铁路客车厂 or 造厂和铁路客车制造厂项目. The Burmese project title is လူစီးတြဲ၊ ကုန္တြဲသစ္တည္ေဆာက္ေရး. 2. The China Eximbank loan that supported this project is not included in the Overseas Development Finance Dataset that Boston University’s Global Development Policy Center published in December 2020. 3. Myanmar’s Ministry of National Planning and Economic Development puts the face value of the China Eximbank loan at $47.51 million. 4. An additional China Eximbank PBC was issued for a Locomotive Construction Plant Project on October 18, 2013 (captured via Record ID#64081).