China Eximbank provides loan for Lobito Port Restoration and Extension Project

Commitment Year2010Country of ActivityAngolaDirect Recipient Country of IncorporationAngolaSectorTransport And StorageFlow TypeLoan

Status

Project lifecycle

Completion

Pipeline: PledgePipeline: CommitmentImplementationCompletion

Timeline

Key dates

Commitment date
Jan 1, 2010
Start (actual)
Jul 3, 2008
End (actual)
Nov 30, 2013

Geospatial footprint

Map overview

Visualizes the AidData-provided feature geometry for this project.

Loading map…

Lobito- more detailed locational information can be found at https://www.openstreetmap.org/way/191362907

Stakeholders

Organizations involved in projects and activities supported by financial and in-kind transfers from Chinese government and state-owned entities

Ultimate beneficial owners

At least 25% host country ownership

Funding agencies

State-owned Policy Banks

  • Export-Import Bank of China (China Eximbank)

Receiving agencies

Government Agencies

  • Government of Angola

Implementing agencies

Government Agencies

  • Government of Angola

State-owned companies

  • China Harbour Engineering Co., Ltd. (CHEC)

Loan desecription

China Eximbank provides loan for Lobito Port Restoration and Extension Project

Interest typeUnknown

Narrative

Full Description

Project narrative

In 2010, the $1.2 billion Lobito Port Restoration and Extension Project was financed with support from China Eximbank. The face value and borrowing terms of the China Eximbank loan are unknown. Construction began on July 3, 2008 and was undertaken by China Harbour Engineering Company (CHEC). The project was completed on November 30, 2013. A handover ceremony for the project was held on December 11, 2013. However, the port is reportedly not yet fully operational. Also, shore cranes are reportedly not working, and stevedoring is done by cranes with a low productivity of 12 moves per hour per vessel. Porto do Lobito is managed and operated by Empresa Portuária do Lobito (EPLo). The Lobito port was refurbished in anticipation of the completion of the Benguela railway for the export of copper and other minerals from Zambia and the DRC.

Staff comments