China Eximbank provides $26.9 million export seller's credit for 132 kV al-Hiswa-Khormakser Transmission and Transformation Project (Linked to Record ID#64621)

Commitments (Constant USD, 2023)$56,696,866
Commitment Year2004Country of ActivityYemenDirect Recipient Country of IncorporationYemenSectorEnergyFlow TypeLoan

Status

Project lifecycle

Implementation

Pipeline: PledgePipeline: CommitmentImplementationCompletion

Timeline

Key dates

Commitment date
Feb 22, 2004

Geospatial footprint

Map overview

Visualizes the AidData-provided feature geometry for this project.

Loading map…

This project involved the construction of a 132 kV electricity transmission line from the al-Hiswa Power Station (محطة الحسوة الأيام or محطة الحسوة البخارية) to the town of Khormakser (خور مكسر) near the port city of Aden. More detailed locational information can be found at: https://www.openstreetmap.org/way/121834063.

Stakeholders

Organizations involved in projects and activities supported by financial and in-kind transfers from Chinese government and state-owned entities

Ultimate beneficial owners

At least 25% host country ownership

Funding agencies

State-owned Policy Banks

  • Export-Import Bank of China (China Eximbank)

Receiving agencies

Government Agencies

  • Government of Yemen

State-owned companies

  • China Machinery Engineering Corporation (CMEC)

Implementing agencies

State-owned companies

  • China Machinery Engineering Corporation (CMEC)

Loan description

China Eximbank provides $26.9 million export seller's credit for 132 kV al-Hiswa-Khormakser Transmission and Transformation Project

Interest typeUnknown

Narrative

Full Description

Project narrative

On February 22, 2004, China Machinery Engineering Corporation (CMEC) and the Government of Yemen signed a $26,950,557.60 supplier credit (vendor financing) agreement for the 132 kV al-Hiswa-Khormakser Transmission and Transformation Project. This agreement was signed into law on June 5, 2005 (Law No. 31 of 2005). The borrowing terms of the supplier’s credit, which CMEC provided with support from an export seller’s credit from China Eximbank, are unknown. The borrower was to use the proceeds from the supplier credit to finance approximately 80% of the $28 million cost of an EPC contract with CMEC. The project involved the construction of a 132 kV electricity transmission line from the al-Hiswa Power Station (محطة الحسوة الأيام or محطة الحسوة البخارية) to the town of Khormakser (خور مكسر) near the port city of Aden. CMEC also provided a supplier credit for the 60 MW al-Hiswa Power Station Expansion Project (see Record ID#64621).

Staff comments

1. This project is also known as the 132 kV al-Hiswa-Khor Maksar Transmission and Transformation Project. The Chinese project title is 哈斯瓦(HISWA)至克豪?克萨(KHORMAKSAR)132千伏输变电项目 or 也门输变电项目. The Arabic project title is مشروع خط النقل (132 ك.ف) الحسوة/ خورمكسر or مشروع تصريف الطاقة الحسوة خور مكسر or مشروع نقل الطاقة الحسوة خور مكسر.