Project ID: 64653

MCC-JJJ Mining Development Ltd provides $473 million syndicated shareholder loan for Ramu Nickel-Cobalt Project (Linked to Project ID#64520)

Commitment amount

$ 721129141.0819011

Adjusted commitment amount

$ 721129141.08

Constant 2021 USD

Summary

Funding agency [Type]

MCC-JJJ Mining Development Company Limited [State-owned Company]

Recipient

Papua New Guinea

Sector

Industry, mining, construction (Code: 320)

Flow type

Loan

Level of public liability

Private debt

Infrastructure

Yes

Category

Intent

Mixed (The next section lists the possible statuses.)

Commercial

Development

Representational

Mixed

Financial Flow Classification

OOF-like (The next section lists the possible statuses.)

Official Development Assistance

Other Official Flows

Vague (Official Finance)

Flows categorized based on OECD-DAC guidelines

Project lifecycle

Status

Completion (The next section lists the possible statuses.)

Pledge

Commitment

Implementation

Completion

Suspended

Cancelled

Milestones

Commitment

2008-07-23

Actual start

2006-11-02

Actual complete

2012-12-06

Geography

Description

In 2004, China Metallurgical Group Co. Ltd. signed a development framework agreement with the Papua New Guinea government and foreign partner companies, Highlands Pacific Company Co Ltd and PNG stakeholders Mineral Resources Development Company (MRDC), for the development of the Ramu Nickel-Cobalt Project. In 2005, China Metallurgical Group and its partners signed a 'Master Agreement' and an 'Association Agreement' to establish a framework for financing the Ramu Nickel-Cobalt Project. Then, on July 23, 2008, MCC Ramu NiCo Ltd. — a special purpose vehicle and wholly owned subsidiary of MCC-JJJ Mining Development Co. — finalized a $1.4 billion financing package necessary to complete the Ramu Nickel-Cobalt Mine Project. The project was financed according to a debt-to-equity ratio of 70:30. 40% of the total project cost was financed through a China Eximbank loan worth $560 million (captured in Project ID#64520) and 30% of the total project cost was financed through a 10-year, $473 million syndicated shareholder loan from MCC-JJJ Mining Development Company Ltd. The loans were to be repaid by 2017 (8 years from the commissioning date of the mine). The interest rate of the USD-denominated loan was set to LIBOR (3.119%) plus a 1.6% margin and the interest rate of the RMB-denominated loan was approximately 4.7%. The remaining project costs were financed via shareholder equity contributions. The Ramu Nickel-Cobalt Project is located in Madang Province on the north coast of Papua New Guinea. The project comprises the Kurumbukari (“KBK”) mine and a beneficiation plant (designed to treat around 4.6 million tons of ore per annum), located on the Kurumbukari plateau, in the foothills of the Bismarck Ranges, 600-800 meters above sea level and 75 kilometers (“km”) to the southwest of the provincial capital of Madang, and the Basamuk processing plant located on the coast, approximately 55 km southeast of Madang. The KBK mine is at latitude 5° 34´ S and longitude 145° 13´ E and the Basamuk refinery is at latitude 5° 32´ S and longitude 145° 8´E. Beneficiated ore is pumped from the mine as a slurry to the plant via a 135km pipeline. The Basamuk plant is designed to produce a mixed nickel-cobalt hydroxide product containing around 32,600 tonnes nickel and 3,300 tonnes cobalt on an annual basis. China Metallurgical Group Co Ltd was the EPC contractor responsible for implementation. On November 3, 2006, a foundation laying ceremony took place. However, the implementation of the project was delayed for two years due to legal appeals over environmental issues. Also, in January 2008, local landowners staged a protest against the project Managers from China Metallurgical Group Co Ltd and four local chiefs held crisis talks in Madang town over a range of grievances. The landowners demanded that China Metallurgical Group Co Ltd stop operations until the dispute was settled. The landowners presented 18 points, complaining about their lack of participation in spin-off business, the employment of heavily armed Chinese security guards, discrimination at the work site and language barriers. One month earlier, a former PNG health minister, Sir Peter Barter, called for an independent environmental impact assessment (EIA) of the project after discrediting the existing EIA. PNG's Lutheran head bishop, Doctor Wesley Kigasung, also warned that pollution from the mine could cause up to 80,000 sea-dependent locals to lose their livelihoods. The project was ultimately completed and handed over on December 6, 2012. In 2014, local rioting broke out against Chinese workers at the KBK mine. Then, in February 2020, a coalition of more than 5,000 villagers and a provincial government in Papua New Guinea sued MCC Ramu NiCo Ltd., demanding not only that its Chinese owners pay restitution totaling 18 billion kina ($5.2 billion), but also that it stop dumping mine waste into the ocean and remediate the allegedly contaminated waters. Half a million people rely on the local fisheries in the Coral Triangle biodiversity hot spot, and the plaintiffs argue that their lives and food supply are at stake. The lawsuit appears to seek the highest environmental damages in the country’s history, and it relies on some of the biggest studies on the ocean dumping of mine waste ever conducted. The tipping point for the lawsuit was an August 2019 slurry spill that caught the eye of the international press as photos of crimson-red ocean waters circulated. Dead fish and a poisoned baby dolphin washed up on shore, and a man died from a “cocktail of heavy metals,” the lawsuit alleges. Madang Governor Peter Yama, who has opposed the Ramu project for years, reportedly called the spill “the worst environmental disaster in Papua New Guinea history.”

Additional details

1. The Ramu Nickel-Cobalt Project is a joint venture between MCC Ramu NiCo Ltd., which has 85% ownership and is the operator of the project, and Ramu Nickel Limited, a wholly owned subsidiary of Highlands Pacific Limited with an 8.56% interest, and Mineral Resources Madang Limited and Mineral Resources Ramu Limited which hold 2.5% and 3.94% interest respectively, and which are both subsidiaries of Mineral Resource Development Corporation (MRDC). MRDC is a PNG Government entity which holds the government and landowners’ interests. Highlands Pacific Limited is a wholly-owned subsidiary of Cobalt 27 following completion of a Scheme of Arrangement in May 2019. 2. MCC-JJJ Mining Development Co. is a joint venture that is owned by 4 Chinese companies: Jinchuan Group Co Ltd (6.98%), Jilin Jien Nickel Industry (13%), Jiuquan Iron and Steel Group Co Ltd (13%), and China Metallurgical Group Co Ltd (67.02%). Under the 2005 Association Agreement, the four Chinese companies participating in MCC-JJJ Mining Development Co. agreed to supply the 30% equity contribution on behalf of all joint venture partners. As a result, the 15% of the equity ($63 million) which was to be invested by Highlands Pacific and Mineral Resources Development was also be funded by MCC-JJJ Mining Development Co. as a loan. In total, MCC-JJJ Mining Development Co. agreed to fund 60% of the total project costs ($840 million). Based on the shareholdings of the Chinese companies in MCC-JJJ Mining Development Co., the total contributions from shareholders in the forms of both loans and equity are: $512 million from MCC, $109 million from Jiuquan Iron & Steel, $109 million from Jilin Jien Nickel Industry, and $109 million from Jinchuan Group. 3. This project is also known as the Kurumbukari Mine Project, the Ramu Nickel Cobalt Project, or the Ramu River Project. The Chinese project title is 拉姆镍矿 or 中冶拉姆镍矿项目. 4.
It is unclear which loan was denominated in USD and which loan was denominated in RMB, AidData has coded the all-in interest rate field based on the assumption the applicable rate was average 6-month LIBOR in July 2008 (3.119%) plus a 1.6% margin. This issue warrants further investigation.

Number of official sources

7

Number of total sources

12

Download the dataset

Details

Cofinanced

Yes

Cofinancing agencies [Type]

Export-Import Bank of China (China Eximbank) [State-owned Policy Bank]

Direct receiving agencies [Type]

MCC Ramu NiCo Ltd. [Joint Venture/Special Purpose Vehicle]

Implementing agencies [Type]

China Metallurgical Group Corporation [State-owned Company]

Loan Details

Maturity

10 years

Interest rate

4.719%

Grant element (OECD Grant-Equiv)

18.2304%

Syndicated loan

Investment project loan

Project finance