Project ID: 64761

Chinese Government provides RMB 119 million interest-free loan — via ETCA — for 69.44 km Laos Section of the Kunming-Bangkok Highway Project (Linked to Project ID#64230, #64231)

Commitment amount

$ 35935055.088519186

Adjusted commitment amount

$ 35935055.09

Constant 2021 USD

Summary

Funding agency [Type]

China Ministry of Commerce [Government Agency]

Recipient

Laos

Sector

Transport and storage (Code: 210)

Flow type

Loan

Level of public liability

Central government debt

Infrastructure

Yes

Category

Intent

Development (The next section lists the possible statuses.)

Commercial

Development

Representational

Mixed

Financial Flow Classification

ODA-like (The next section lists the possible statuses.)

Official Development Assistance

Other Official Flows

Vague (Official Finance)

Flows categorized based on OECD-DAC guidelines

Project lifecycle

Status

Completion (The next section lists the possible statuses.)

Pledge

Commitment

Implementation

Completion

Suspended

Cancelled

Milestones

Commitment

2002-11-03

Actual start

2004-04-26

Actual complete

2008-03-31

Geography

Description

On November 3, 2002, the Chinese Government and the Government of Laos signed an Economic and Technical Cooperation Agreement (ETCA), which committed funding for the 69.44 km Laos Section of the Kunming-Bangkok Highway Project. China’s Ministry of Commerce (MOFCOM) made three separate financial commitments in support of this project: RMB 119 million interest-free loan (captured in Project ID#64761) RMB 80 million interest-free loan (captured in Project ID#64231) RMB 50 million grant (captured in Project ID#64230) The proceeds from the grant and the interest-free loans were used to finance a construction contract between the Ministry of Communications, Transport, Post and Construction (MCTPC) of Laos and Yunnan Sunshine Road and Bridge Co., Ltd., which was signed on April 7, 2004. The total cost of the larger 247 km Kunming-Bangkok Highway Project was approximately $100 million and it was co-financed by the Government of Thailand and the Asian Development Bank. The Laos Section of the Kunming-Bangkok Highway Project involved the construction of a 69.44 km segment of Route 3 (R3) that runs from the border crossing in Mohan/Boten (Yunnan) to the town of Nateuy and then from Nateuy to the town of Luang Namtha (Luangnamtha) within Luang Namtha (Luangnamtha) Province. Yunnan Sunshine Road and Bridge Co., Ltd. was the contractor responsible for implementation. A groundbreaking ceremony was held on April 26, 2004. The project was completed on March 31, 2008.

Additional details

1. This project is also known as the Laos Section of the Route 3 (R3) Project or the PRC Section K00+000-K67+720 of the Houayxay-Boten Road Construction Project. 2. The Chinese project title is 昆曼公路老挝段项目 or 昆曼公路 or 昆曼高速公路. 3. Yunnan Sunshine Road and Bridge Co., Ltd. is also known as Yunnan Highway & Bridge Co., Ltd. 4. Since the borrowing terms of the interest-free loan are unavailable, AidData has set the maturity to 20 years by default and grace period to 10 years by default, per China's Foreign Assistance White Paper (http://www.cidca.gov.cn/2018-08/06/c_129925064_3.htm) which states that the maturity of interest-free loans is 20 years, with a drawdown period of 5 years, grace period of 5 years, and repayment over 10 years. AidData treats the drawdown period as providing 5 years of additional grace.

Number of official sources

4

Number of total sources

10

Download the dataset

Details

Cofinanced

No

Direct receiving agencies [Type]

Government of Laos [Government Agency]

Implementing agencies [Type]

Yunnan Road and Bridge Co., Ltd. [State-owned Company]

Loan Details

Maturity

20 years

Interest rate

0.0%

Grace period

10 years

Grant element (OECD Grant-Equiv)

71.6021%

Bilateral loan

Interest-free loan

Investment project loan