Chinese Government provides RMB 450,000 grant for feasibility study Asphalt Processing Plant Project in El Alto

Commitments (Constant USD, 2023)$77,310
Commitment Year2012Country of ActivityBoliviaDirect Recipient Country of IncorporationBoliviaSectorIndustry, Mining, ConstructionFlow TypeGrant

Status

Project lifecycle

Completion

Pipeline: PledgePipeline: CommitmentImplementationCompletion

Timeline

Key dates

Commitment date
Jan 22, 2012
End (actual)
Sep 1, 2012

Geospatial footprint

Map overview

Visualizes the AidData-provided feature geometry for this project.

Loading map…

The project funds an asphalt processing plant in El Alto, Bolivia. More detailed locational information can be found at https://www.openstreetmap.org/relation/4499832

Stakeholders

Organizations involved in projects and activities supported by financial and in-kind transfers from Chinese government and state-owned entities

Funding agencies

Government Agencies

  • China Ministry of Commerce

Receiving agencies

Government Agencies

  • Government of Bolivia

Loan description

Chinese Government provides RMB 450,000 grant for feasibility study Asphalt Processing Plant Project in El Alto

Narrative

Full Description

Project narrative

On January 22, 2012, the Chinese Government and the Government of Bolivia signed letters of exchange, which committed RMB 450,000 of grant funding for a feasibility study of the Asphalt Processing Plant Project in the city of El Alto. As of September 14 2012, the plant was functional and being used for road projects.

Staff comments

1. The Bolivian Ministry of Foriegn Relations associates two dates with the feasibility study: January 22, 2012 and February 6, 2012. It is unclear which of these dates pertains to the exchange of letters and which pertains to the grant.