Project ID: 66257

Chinese Government provides RMB 60 million grant — via an ETCA — for the Beijing Street Rehabilitation Project

Commitment amount

$ 12344881.016792137

Adjusted commitment amount

$ 12344881.02

Constant 2021 USD

Summary

Funding agency [Type]

China Ministry of Commerce [Government Agency]

Recipient

Mongolia

Sector

Transport and storage (Code: 210)

Flow type

Grant

Infrastructure

No

Category

Intent

Development (The next section lists the possible statuses.)

Commercial

Development

Representational

Mixed

Financial Flow Classification

ODA-like (The next section lists the possible statuses.)

Official Development Assistance

Other Official Flows

Vague (Official Finance)

Flows categorized based on OECD-DAC guidelines

Project lifecycle

Status

Completion (The next section lists the possible statuses.)

Pledge

Commitment

Implementation

Completion

Suspended

Cancelled

Milestones

Commitment

2010-06-01

Actual start

2014-05-22

Planned complete

2014-12-01

Actual complete

2014-10-27

Geography

Description

On June 1, 2010, the Chinese Government and the Government of Mongolia signed an exchange of letters, which committed RMB 60 million of grant funding for the Beijing Street Rehabilitation Project. The grant proceeds were drawn from an Economic and Technical Cooperation Agreement (ETCA) that the two governments signed on April 11, 2008. The purpose of the project was to rehabilitate an 897 meter street (‘Beijing Street’) — located in front of the Chinese Embassy — in the city of Ulaanbaatar’s Bayanzurkh district. The project also involved the installation of lighting, traffic safety infrastructure, and ‘greening facilities.’ Beijing Construction Engineering Group (BCEG) was the contractor responsible for implementation. On September 10, 2013. It signed a project implementation agreement (MOU) with the municipality of Ulaanbaatar. Construction began on May 22, 2014 and the road was opened to traffic on October 27, 2014. The project was officially completed on December 6, 2014. The originally anticipated project completion date was November 31, 2014. The project was eventually awarded the "Special Prize for Capital Engineering Construction" by the Mongolian Government.

Additional details

The Chinese project title is 北京街道路改造项目 or 北京街项目. The Mongolian project title is хотын Бээжингийн гудамжны замыг шиэчлэн тохижуулах төслийг or Бээжингийн гудамж байгуулах талаарх. The Mongolian translation of the June 1, 2010 grant agreement is Монгол Улсад Улаанбаатар хотын Бээжингийн гудамжны замыг шиэчлэн тохижуулах төслийг хэрэгжүүлэх тухай Монгол Улсын Засгийн газар, БНХАУ-ын Засгийн газар хоорондын солилцох захидал). As this is an ETCA, which is a financing mechanism specific to China's Ministry of Commerce (MOFCOM), AidData has coded MOFCOM as the specific Chinese Government institution responsible for providing this grant.

Number of official sources

7

Number of total sources

12

Download the dataset

Details

Cofinanced

No

Direct receiving agencies [Type]

Government of Mongolia [Government Agency]

Implementing agencies [Type]

Beijing Construction Engineering Group Co., Ltd. (BCEG) [State-owned Company]