China Eximbank provides $20.08 million preferential buyer’s credit for 67km Tosontsengel-Uliastai Road Construction Project (Linked to Project ID#40435)
Commitment amount
$ 21894841.330084663
Adjusted commitment amount
$ 21894841.33
Constant 2021 USD
Summary
Funding agency [Type]
Export-Import Bank of China (China Eximbank) [State-owned Policy Bank]
Recipient
Mongolia
Sector
Transport and storage (Code: 210)
Flow type
Loan
Level of public liability
Central government debt
Infrastructure
Yes
Category
Project lifecycle
Geography
Description
On May 31, 2006, the Mongolian Parliament provided in-principle approval to the Ministry of Finance to borrow $500 million from China Eximbank. Then, on June 16, 2011, China Eximbank and the Government of Mongolia signed a general loan agreement regarding the utilization of a $500 million preferential buyer's credit (PBC) for various projects (see Umbrella Project ID#40435). Under the terms of the general loan agreement, all subsidiary (individual) loan agreements for specific projects carry identical borrowing terms: a 20-year maturity, a 7-year grace period, a 2% interest rate, a 0% default (penalty) interest rate, a 0.25% commitment fee, and a 0% management fee. Nearly seven years later, on September 17, 2018, U.Enkhtuvshin, Deputy Prime Minister of Mongolia, and Zhong Shan, Commerce Minister of China, signed a subsidiary China Eximbank loan (PBC) agreement [CHINA EXIMBANK PBC 2018 (22) TOTAL NO. (479)] worth $20,089,779.69 for the 67 km Tosontsengel-Uliastai Road Construction Project. The proceeds of the PBC were to be used by the borrower to finance 100% of the $20,089,779.69 cost of a commercial contract [contract number 31 and project number ABZ-2018] between Mongolia’s Ministry of Road and Transportation and China Communications Construction Company, Ltd. (CCCC), which was signed on March 12, 2018. The purpose of the project is to construct a 67 km paved road between Tosontsengel and Uliastai. Upon completion, the road will connect the center of Zavkhan aimag with the capital city and pass through Zagastai pass, a difficult pass of the Tarvagatai mountain range. The project has two components: a 28.11 km stretch road known as PK0 + 000-PK28 + 110 and 36.37 km stretch of road known as PK28 + 110-PK64 + 480. China Communications Construction Company, Ltd. (CCCC), Arj Road LLC and Tum Arvijikh LLC are the contractors responsible for project implementation. A protocol agreement on the project was signed on August 30, 2016. Land acquisition issues were subsequently addressed through a government resolution that was issued on May 2, 2017. Project implementation was originally expected to commence in 2018. It was not until June 7, 2019 that the contractors were given permission to begin construction. Construction activities began in July 2019. As of November 15, 2019, the project had achieved a 34.5% completion rate. As of May 21, the project had achieved a 76.5% completion rate. As of August 27, 2021, the project had achieved a 98% completion rate. The project was ultimately completed on June 27, 2022. The project’s originally scheduled completion date was October 30, 2020. Implementation delays resulted from unresolved funding issues for the project's supervisory consulting services.
Additional details
1. The Mongolian project title is Улиастай-Тосонцэнгэл чиглэлийн 67 км автозам барих төсөл. The Chinese project title is 扎布汗省公路项目. 2. The China Eximbank loan that supported this project is not included in the Overseas Development Finance Dataset that Boston University’s Global Development Policy Center published in December 2020. 3. The bidding invitation for the project can be accessed in its entirety via https://www.dropbox.com/s/psoc69o655pxjam/%D0%A2%D0%91%D0%91-%D0%A2%D0%BE%D1%81%D0%BE%D0%BD%D1%86%D1%8D%D0%BD%D0%B3%D1%8D%D0%BB-%D0%A3%D0%BB%D0%B8%D0%B0%D1%81%D1%82%D0%B0%D0%B9%20%D1%87%D0%B8%D0%B3%D0%BB%D1%8D%D0%BB%D0%B8%D0%B9%D0%BD%2067%20%D0%BA%D0%BC%20%D1%85%D0%B0%D1%82%D1%83%D1%83%20%D1%85%D1%83%D1%87%D0%B8%D0%BB%D1%82%D1%82%D0%B0%D0%B9%20%D0%B0%D0%B2%D1%82%D0%BE%20%D0%B7%D0%B0%D0%BC-%D1%88%D1%83%D1%83%D0%B4%20%D0%B3%D1%8D%D1%80%D1%8D%D1%8D%20%D0%B1%D0%B0%D0%B9%D0%B3%D1%83%D1%83%D0%BB%D0%B0%D1%85.pdf?dl=0. 4. The loan (PBC) agreement can be accessed in its entirety via https://www.dropbox.com/s/18gg8m0ey59m3ss/Mongolia%202018%20China%20Eximbank%20Loan%20for%20Construction%20of%20Tosontsengel-Uliatsai%20Direction%2067km%20Road%20Project.pdf?dl=0
Number of official sources
9
Number of total sources
19
Details
Cofinanced
No
Direct receiving agencies [Type]
Government of Mongolia [Government Agency]
Implementing agencies [Type]
China Communications Construction Co., Ltd. (CCCC) [State-owned Company]
Arj Capital LLC [Private Sector]
Tum Arvijikh LLC [Private Sector]
Loan Details
Maturity
20 years
Interest rate
2.0%
Grace period
7 years
Grant element (OECD Grant-Equiv)
41.4817%