Project ID: 66277

China Eximbank provides $20.08 million preferential buyer’s credit for 67km Tosontsengel-Uliastai Road Construction Project (Linked to Project ID#40435)

Commitment amount

$ 21894841.330084663

Adjusted commitment amount

$ 21894841.33

Constant 2021 USD

Summary

Funding agency [Type]

Export-Import Bank of China (China Eximbank) [State-owned Policy Bank]

Recipient

Mongolia

Sector

Transport and storage (Code: 210)

Flow type

Loan

Level of public liability

Central government debt

Infrastructure

Yes

Category

Intent

Mixed (The next section lists the possible statuses.)

Commercial

Development

Representational

Mixed

Financial Flow Classification

OOF-like (The next section lists the possible statuses.)

Official Development Assistance

Other Official Flows

Vague (Official Finance)

Flows categorized based on OECD-DAC guidelines

Project lifecycle

Status

Completion (The next section lists the possible statuses.)

Pledge

Commitment

Implementation

Completion

Suspended

Cancelled

Milestones

Commitment

2018-09-17

Planned start

2018-01-01

Actual start

2019-06-07

Planned complete

2020-10-30

Actual complete

2022-06-27

NOTE: Red circles denote delays between planned and actual dates

Geography

Description

On May 31, 2006, the Mongolian Parliament provided in-principle approval to the Ministry of Finance to borrow $500 million from China Eximbank. Then, on June 16, 2011, China Eximbank and the Government of Mongolia signed a general loan agreement regarding the utilization of a $500 million preferential buyer's credit (PBC) for various projects (see Umbrella Project ID#40435). Under the terms of the general loan agreement, all subsidiary (individual) loan agreements for specific projects carry identical borrowing terms: a 20-year maturity, a 7-year grace period, a 2% interest rate, a 0% default (penalty) interest rate, a 0.25% commitment fee, and a 0% management fee. Nearly seven years later, on September 17, 2018, U.Enkhtuvshin, Deputy Prime Minister of Mongolia, and Zhong Shan, Commerce Minister of China, signed a subsidiary China Eximbank loan (PBC) agreement [CHINA EXIMBANK PBC 2018 (22) TOTAL NO. (479)] worth $20,089,779.69 for the 67 km Tosontsengel-Uliastai Road Construction Project. The proceeds of the PBC were to be used by the borrower to finance 100% of the $20,089,779.69 cost of a commercial contract [contract number 31 and project number ABZ-2018] between Mongolia’s Ministry of Road and Transportation and China Communications Construction Company, Ltd. (CCCC), which was signed on March 12, 2018. The purpose of the project is to construct a 67 km paved road between Tosontsengel and Uliastai. Upon completion, the road will connect the center of Zavkhan aimag with the capital city and pass through Zagastai pass, a difficult pass of the Tarvagatai mountain range. The project has two components: a 28.11 km stretch road known as PK0 + 000-PK28 + 110 and 36.37 km stretch of road known as PK28 + 110-PK64 + 480. China Communications Construction Company, Ltd. (CCCC), Arj Road LLC and Tum Arvijikh LLC are the contractors responsible for project implementation. A protocol agreement on the project was signed on August 30, 2016. Land acquisition issues were subsequently addressed through a government resolution that was issued on May 2, 2017. Project implementation was originally expected to commence in 2018. It was not until June 7, 2019 that the contractors were given permission to begin construction. Construction activities began in July 2019. As of November 15, 2019, the project had achieved a 34.5% completion rate. As of May 21, the project had achieved a 76.5% completion rate. As of August 27, 2021, the project had achieved a 98% completion rate. The project was ultimately completed on June 27, 2022. The project’s originally scheduled completion date was October 30, 2020. Implementation delays resulted from unresolved funding issues for the project's supervisory consulting services.

Additional details

1. The Mongolian project title is Улиастай-Тосонцэнгэл чиглэлийн 67 км автозам барих төсөл. The Chinese project title is 扎布汗省公路项目. 2. The China Eximbank loan that supported this project is not included in the Overseas Development Finance Dataset that Boston University’s Global Development Policy Center published in December 2020. 3. The bidding invitation for the project can be accessed in its entirety via https://www.dropbox.com/s/psoc69o655pxjam/%D0%A2%D0%91%D0%91-%D0%A2%D0%BE%D1%81%D0%BE%D0%BD%D1%86%D1%8D%D0%BD%D0%B3%D1%8D%D0%BB-%D0%A3%D0%BB%D0%B8%D0%B0%D1%81%D1%82%D0%B0%D0%B9%20%D1%87%D0%B8%D0%B3%D0%BB%D1%8D%D0%BB%D0%B8%D0%B9%D0%BD%2067%20%D0%BA%D0%BC%20%D1%85%D0%B0%D1%82%D1%83%D1%83%20%D1%85%D1%83%D1%87%D0%B8%D0%BB%D1%82%D1%82%D0%B0%D0%B9%20%D0%B0%D0%B2%D1%82%D0%BE%20%D0%B7%D0%B0%D0%BC-%D1%88%D1%83%D1%83%D0%B4%20%D0%B3%D1%8D%D1%80%D1%8D%D1%8D%20%D0%B1%D0%B0%D0%B9%D0%B3%D1%83%D1%83%D0%BB%D0%B0%D1%85.pdf?dl=0. 4. The loan (PBC) agreement can be accessed in its entirety via https://www.dropbox.com/s/18gg8m0ey59m3ss/Mongolia%202018%20China%20Eximbank%20Loan%20for%20Construction%20of%20Tosontsengel-Uliatsai%20Direction%2067km%20Road%20Project.pdf?dl=0

Number of official sources

9

Number of total sources

19

Download the dataset

Details

Cofinanced

No

Direct receiving agencies [Type]

Government of Mongolia [Government Agency]

Implementing agencies [Type]

China Communications Construction Co., Ltd. (CCCC) [State-owned Company]

Arj Capital LLC [Private Sector]

Tum Arvijikh LLC [Private Sector]

Loan Details

Maturity

20 years

Interest rate

2.0%

Grace period

7 years

Grant element (OECD Grant-Equiv)

41.4817%

Bilateral loan

Export buyer's credit

Investment project loan

Preferential Buyer's Credit