ICBC provides $50.874 million loan for 220kv Lomaum Electricity Transmission Line Construction Project (Linked to Record ID#73911)

Commitments (Constant USD, 2023)$52,602,738
Commitment Year2013Country of ActivityAngolaDirect Recipient Country of IncorporationAngolaSectorEnergyFlow TypeLoan

Status

Project lifecycle

Completion

Pipeline: PledgePipeline: CommitmentImplementationCompletion

Timeline

Key dates

Commitment date
Jan 1, 2013
End (actual)
Jun 1, 2015

Geospatial footprint

Map overview

Visualizes the AidData-provided feature geometry for this project.

Loading map…

This project involves the construction of a 220kv electricity transmission line between Lomaum and Biópio. It also involved the construction of several electricity substations. In 2016, the contract was amended to include two cables from the hydropower station to Biópio (89.4 km) and from Biópio to South Benguela (57 km). More detailed locational information can be found at https://www.openstreetmap.org/way/529028291#map=17/-12.41199/13.78128.

Stakeholders

Organizations involved in projects and activities supported by financial and in-kind transfers from Chinese government and state-owned entities

Ultimate beneficial owners

At least 25% host country ownership

Funding agencies

State-owned Commercial Banks

  • Industrial and Commercial Bank of China (ICBC)

Receiving agencies

Government Agencies

  • Government of Angola

Implementing agencies

State-owned companies

  • Guangxi Hydroelectric Construction Bureau (GHCB)
  • Kanazuro Electric, S.A.

Loan desecription

ICBC provides $50.874 million loan for 220kv Lomaum Electricity Transmission Line Construction Project

Interest typeUnknown

Narrative

Full Description

Project narrative

On 9 December 2013, the Government of Angola issued a presidential order (No. 128/13), approving a $50,874,466.37 loan from the Industrial and Commercial Bank of China (ICBC) for the 220kv Lomaum Electricity Transmission Line Construction Project. The loan terms are unknown. This project involves the construction of a 220kv electricity transmission line between Lomaum and Biópio. It also involved the construction of several electricity substations. The purpose of this project is to evacuate power from the ICBC-financed Lomaum Hydroelectric Power Plant (see Record ID#73911). Guangxi Hydroelectric Construction Bureau was the contractor responsible for constructing the transmission line. On 7 June 2016, the President of Angola authorized an a proposal to increase the contract cost by $8.191 million to cover the erection of two cables from the hydropower station to Biópio (89.4 km) and from Biópio to South Benguela (57 km). but it is unclear if this increase was also covered by ICBC.

Staff comments

The Chinese project title is 安哥拉洛玛乌电站出线工程. This loan is not In the database of Chinese loan commitments that SAIS-CARI released in July 2020.