China Eximbank provides loan for Zaire Provincial Hospital Construction Project

Commitment Year2012Country of ActivityAngolaDirect Recipient Country of IncorporationAngolaSectorHealthFlow TypeLoan

Status

Project lifecycle

Implementation

Pipeline: PledgePipeline: CommitmentImplementationCompletion

Timeline

Key dates

Commitment date
Jan 1, 2012
Start (actual)
Nov 7, 2013

Geospatial footprint

Map overview

Visualizes the AidData-provided feature geometry for this project.

Loading map…

This hospital is located in Kiowa, on the outskirts of the city of M'banza Kongo (Mbanza-Kongo), which is the capital of Zaire Province. More detailed locational information can be found at https://www.openstreetmap.org/way/1112639458 and https://www.google.com/maps/place/Zaire+Provincial+Hospital/@-6.2622858,14.2460055,18.76z/data=!4m6!3m5!1s0x1a4480fb6b08afe1:0x5163930031b1a3c9!8m2!3d-6.2624!4d14.2467!16s%2Fg%2F11s36vbwbl?entry=ttu.

Stakeholders

Organizations involved in projects and activities supported by financial and in-kind transfers from Chinese government and state-owned entities

Ultimate beneficial owners

At least 25% host country ownership

Funding agencies

State-owned Policy Banks

  • Export-Import Bank of China (China Eximbank)

Receiving agencies

Government Agencies

  • Government of Angola

Implementing agencies

Government Agencies

  • Government of Angola

State-owned companies

  • China Road & Bridge Corporation (CRBC)

Loan description

China Eximbank provides loan for Zaire Provincial Hospital Construction Project

Interest typeUnknown

Narrative

Full Description

Project narrative

On 20 August, 2012, Angola's Minister of Health laid the cornerstone for the Zaire Provincial Hospital Construction Project. This project was reportedly financed by a China Eximbank loan. The value and terms of this loan are unknown. The total project cost was estimated to be about $42 million. This hospital is located in Kiowa, on the outskirts of the city of M'banza Kongo (Mbanza-Kongo), which is the capital of Zaire Province. It was supposed to be the largest comprehensive hospital in Zaire Province, with a total construction area of about 23,000 square meters and 332 beds. China Road and Bridge Corporation (CRBC) was the contractor responsible for implementation. Construction began on 7 November 2013. Then, on 1 June, 2014, several Chinese MOFCOM officials inspected the project site. It is unknown whether of when this project was completed.

Staff comments

The Chinese project title is 安哥拉扎伊尔省医院项目 or 扎伊尔省总医院. This loan is not included in the database of Chinese loan commitments that SAIS-CARI released in July 2020. China Eximbank reportedly issued a subsidiary loan through a credit line for this project; however, the specific credit line that was utilized is unknown (See: "OBRAS DE CONSTRUÇÃO DO NOVO HOSPITAL ORÇADAS EM QUATRO MIL MILHÕES DE KWANZAS").