China National Electric Wire & Cable Import & Export Corporation gives 1.45 billion BDK suppliers credit for Bogra-Barapukuria 230 KV Transmission Line Project

Commitments (Constant USD, 2023)$45,313,100
Commitment Year2005Country of ActivityBangladeshDirect Recipient Country of IncorporationBangladeshSectorEnergyFlow TypeLoan

Status

Project lifecycle

Completion

Pipeline: PledgePipeline: CommitmentImplementationCompletion

Timeline

Key dates

Commitment date
Apr 28, 2005
End (actual)
Nov 30, 2005

Geospatial footprint

Map overview

Visualizes the AidData-provided feature geometry for this project.

Loading map…

More detailed locational information can be found at https://www.openstreetmap.org/way/166377802#map=10/25.1994/89.1500

Stakeholders

Organizations involved in projects and activities supported by financial and in-kind transfers from Chinese government and state-owned entities

Ultimate beneficial owners

At least 25% host country ownership

Funding agencies

State-owned companies

  • China National Electric Wire and Cable Import and Export Corporation (CNEWC)

Receiving agencies

State-owned companies

  • Power Grid Company of Bangladesh (PGCB)

Implementing agencies

State-owned companies

  • Power Grid Company of Bangladesh (PGCB)

Guarantors

Government Agencies

  • Government of Bangladesh

Loan description

China National Electric Wire & Cable Import & Export Corporation gives 1.45 billion BDK suppliers credit for Bogra-Barapukuria 230 KV Transmission Line Project

Interest typeUnknown

Narrative

Full Description

Project narrative

In 2005 the Power Grid Company of Bangladesh (PGCB) received 1.45 billion BDK of supplier's credit from China National Electric Wire & Cable Import & Export Corporation for the Bogra-Barapukuria 230 KV Transmission Line Project. The Government of Bangladesh provided a sovereign guarantee for this supplier's credit on April 28, 2005. China National Electric Wire and Cable Import and Export Corporation (CNEWC) will be implementing the project (Contract No. PGCB/SC/011). The project began in 2003 and was finished in November 2005.