Project ID: 69124

Guangzhou International Economic & Technical Cooperation Company (GIETC) provides $60 million suppliers credit for the Expansion and Rehabilitation of 132 KV 33 KV Transmission Line under Phase IV of the Greater Dhaka Electricity Distribution Project

Commitment amount

$ 150872266.04479855

Adjusted commitment amount

$ 150872266.04

Constant 2021 USD

Summary

Funding agency [Type]

Guangzhou International Economic & Technical Cooperation Company (GIETC) [State-owned Company]

Recipient

Bangladesh

Sector

Energy (Code: 230)

Flow type

Loan

Level of public liability

Central government debt

Infrastructure

Yes

Category

Intent

Mixed (The next section lists the possible statuses.)

Commercial

Development

Representational

Mixed

Financial Flow Classification

OOF-like (The next section lists the possible statuses.)

Official Development Assistance

Other Official Flows

Vague (Official Finance)

Flows categorized based on OECD-DAC guidelines

Project lifecycle

Status

Completion (The next section lists the possible statuses.)

Pledge

Commitment

Implementation

Completion

Suspended

Cancelled

Milestones

Commitment

2001-06-17

Planned complete

2003-06-30

Geography

Description

In 2001, the Government of Bangladesh received supplier's credit worth $60 million from Guangzhou International Economic & Technical Cooperation Company (GIETC) for the Expansion and Rehabilitation of 132 KV 33 KV Transmission Line under Phase IV of the Greater Dhaka Electricity Distribution Project. The supplier's credit agreement was reportedly finalized on June 30, 2001. The Government of Bangladesh provided a sovereign guarantee for the supplier's credit on June 17, 2001. The purpose of this project was to construct a nine kilometer 132 KV power supply line, a nine kilometer 132 KV underground cable, a 17 kilometer 33 KV overhead line, a 33 kilometer 33 KV underground cable, and install three 132/33 KV substations with a capacity of 450 MVA. Additionally, through the project, 268 switching stations (11 KV), 82 panels ( 11 KV), a 437.25 kilometer 11 KV underground and aerial cable with necessary accessories, and 1500 pole-mounted sub-stations were to be installed by GIETC. The expected completion date of the project was June 30, 2003. Xinjiang TBEA and Dhaka Power Distribution Company of Bangladesh, signed a contract for the Dhaka smart grid and upgrade project, which exceeded 11.1 billion yuan. This may be an extension of the project signed in 2001.

Additional details

1. The Chinese project title is 孟加拉大达卡地区输变电第四期工程国际

Number of official sources

3

Number of total sources

3

Download the dataset

Details

Cofinanced

No

Direct receiving agencies [Type]

Government of Bangladesh [Government Agency]

Implementing agencies [Type]

Government of Bangladesh [Government Agency]

Guarantee provider [Type]

Government of Bangladesh [Government Agency]

Loan Details

Bilateral loan

Investment project loan

Supplier's credit/Export seller's credit