Skip to content

Overview

China Eximbank provides $381.5 million seller's credit for Merowe Hydroelectric Dam Transmission Lines and Substations Project (Linked to Record ID#178)

Commitments (Constant USD, 2023)$858,314,071
Commitment Year2003Country of ActivitySudanDirect Recipient Country of IncorporationChina (People's Republic of)SectorEnergyFlow TypeLoan

Status

Project lifecycle

Completion

Pipeline: PledgePipeline: CommitmentImplementationCompletion

Timeline

Key dates

Commitment date
Jan 1, 2003
Start (actual)
Apr 9, 2005
End (actual)
Apr 13, 2009

Geospatial footprint

Map overview

Visualizes the AidData-provided feature geometry for this project.

Loading map…

The Merowe Hydroelectric Dam Transmission Lines and Substations Project involved the construction of 1,776 kilometers of electricity transmission lines and seven electricity substations. More specifically, it involved the construction of two 500kv parallel transmission lines from the Merowe Hydroelectric Power Plant to Khartoum (with each line covering 350 km), the construction of two 500/200kv sub-stations in Omdurman and Khartoum North, the construction of a 38 km, 500kv transmission line between the Omdurman and Khartoum North substations, the extension of 240 km, 500kv transmission line to Atbara, the construction of a 500/200kv substation in Atbara, the construction of a 455 km, 220kv, transmission line from Atbara to Port Sudan, the construction of a 220/110kv substation in Port Sudan, the construction of a 310 km, 220kv transmission line from Merowe Dam to Dongola, and the construction of three 220/33kv sub-stations in Merowe, Debba and Dongola. The locational coordinates of the Merowe dam itself are 18°40′08″N 32°03′01″E. More detailed locational information can be found at https://www.openstreetmap.org/relation/3183786, https://www.openstreetmap.org/relation/3183787, https://www.openstreetmap.org/relation/3183791, https://www.openstreetmap.org/way/178486764, https://www.openstreetmap.org/way/230637768, https://www.openstreetmap.org/way/169139609

Stakeholders

Organizations involved in projects and activities supported by financial and in-kind transfers from Chinese government and state-owned entities

Ultimate beneficial owners

At least 25% Chinese ownership

Funding agencies

State-owned Policy Banks

  • Export-Import Bank of China (China Eximbank)

Receiving agencies

Government Agencies

  • Government of Sudan

State-owned companies

  • Harbin Power Equipment Ltd.

Implementing agencies

Government Agencies

  • Sudan Ministry of Finance and National Economy
  • Sudan Ministry of Water Resources, Irrigation and Electricity

State-owned companies

  • China International Water and Electrical Corporation (CWE)
  • Harbin Power Equipment Ltd.
  • Jilin Province Power Transmission and Substation Project Co.
  • Sinohydro Corporation Limited
  • Sudan National Electricity Corporation (NEC Sudan)

Loan description

China Eximbank provides $381.5 million seller's credit for Merowe Hydroelectric Dam Transmission Lines and Substations Project

Interest typeUnknown

Narrative

Full Description

Project narrative

On December 23, 2003, a consortium of Chinese companies signed a $400 million commercial contract for the Merowe Hydroelectric Dam Transmission Lines and Substations Project. The commercial contract was financed by a $381,467,000 million export seller's credit agreement between China Eximbank and Harbin Power Equipment Company (HPEC). It appears that HPEC then on-lent the proceeds of the loan to the Government of Sudan. The borrowing terms that applied to the export seller's credit agreement and the on-lending agreement are unknown. The purpose of this project was to evacuate power from the Merowe Hydroelectric Dam, which was also financed by a $608 million China Eximbank loan (as captured via Record ID#178). It involved the construction of 1,776 kilometers of transmission lines and seven substations. More specifically, the project involved the construction of (1) two 500kv parallel transmission lines from the Merowe Hydroelectric Power Plant to Khartoum, (2) two 500/200kv sub-stations in Omdurman and Khartoum North, (3) a 38 km, 500kv transmission line between the Omdurman and Khartoum North substations, (4) the extension of 240 km, 500kv transmission line to Atbara, (5) a 500/200kv substation in Atbara, (6) a 455 km, 220kv, transmission line from Atbara to Port Sudan, (7) 220/110kv substation in Port Sudan, (8) a 310 km, 220kv transmission line from Merowe Dam to Dongola, and (9) three 220/33kv sub-stations in Merowe, Debba and Dongola. The contractors responsible for project implementation included HPEC, China International Water and Electric Corporation (CWE), China Water Resources and Hydropower Engineering Corporation (CWHEC or Sinohydro), and Jilin Province Power Transmission and Substation Project Company. A formal groundbreaking ceremony took place on April 9, 2005 but the project did not enter the installation phase until January 31, 2006. The largest substation was completed on April 13, 2009. There are some indications that the loan issued for the Merowe Hydroelectric Dam Transmission Lines and Substations Project may have underperformed vis-a-vis lender expectations. According to Sudan’s Finance Minister Ali Mahmood Abdel-Rasool, China Eximbank suspended its financing for 11 projects in Sudan following the secession of South Sudan in July 2011, which triggered a major loss of oil revenue (a key source of collateral for China Eximbank loans). Ali Mahmood Abdel-Rasool said at the time that the Government of Sudan had previously pledged oil revenues (worth 120,000 barrels per day) to China Eximbank as a source of collateral. Then, on February 18, 2012, the Chinese Government announced that it had agreed to reschedule the outstanding debt obligations of the Government of Sudan by extending loan repayment periods by 5 years (as captured via Record ID#30421). According to the External Debt Unit of the Central Bank of Sudan, the Government of Sudan's total arrears to Chinese creditors amounted to $3.864 billion ($2.608 billion in principal, $1.129 billion in interest, and $127 million in penalty interest) as of March 31, 2022.

Staff comments

1. The Chinese project title is 麦罗维输变电项目 or 麦罗维工程输变电项目. 2. It is unclear when China Eximbank issued the export seller's credit agreement. This issue warrants further investigation.