Chinese Government provides ETB 25.4 million grant for Nationwide Wind and Solar Energy Grid Based Master Plan Project

Commitments (Constant USD, 2023)$2,264,603
Commitment Year2010Country of ActivityEthiopiaDirect Recipient Country of IncorporationEthiopiaSectorEnergyFlow TypeGrant

Status

Project lifecycle

Completion

Pipeline: PledgePipeline: CommitmentImplementationCompletion

Timeline

Key dates

Commitment date
Jan 11, 2010
Start (actual)
Feb 15, 2011
End (actual)
Aug 23, 2012

Stakeholders

Organizations involved in projects and activities supported by financial and in-kind transfers from Chinese government and state-owned entities

Funding agencies

Government Agencies

  • China Ministry of Commerce

Receiving agencies

Government Agencies

  • Government of Ethiopia

Implementing agencies

State-owned companies

  • Beijing Construction Engineering Group Co., Ltd. (BCEG)
  • HydroChina International Engineering Co. Ltd

Loan description

Chinese Government provides ETB 25.4 million grant for Nationwide Wind and Solar Energy Grid Based Master Plan Project

Narrative

Full Description

Project narrative

On January 11, 2010, the Chinese Government and the Government of Ethiopia signed letters of exchange with respect to the Nationwide Wind and Solar Energy Grid Based Master Plan Project. According to the Government of Ethiopia’s Aid Management Platform (AMP), China’s Ministry of Commerce agreed to provide a grant to the Government of Ethiopia worth approximately ETB 25,466,201 to support this project. The purpose of the project was to undertake a field investigation of wind and solar energy resources in Ethiopia, prepare an Ethiopian wind and solar energy development master plan, recommend 2 wind farm sites and a photovoltaic power station site, prepare pre-feasibility study reports for the 2 wind farms and photovoltaic power station, and provide a 30-day training of 10 Ethiopian technicians in Ethiopia and China. HydroChina International Engineering Company (HCIE) was the general contractor responsible for project implementation. On February 22, 2011, it signed an RMB 10.8 million contract with China’s Ministry of Commerce (MOFCOM). HCIE was responsible for organizing and managing the wind and solar master plan. Beijing Engineering Corporation was responsible for the implementation and design of the wind and solar master plan. The master plan was released on August 15, 2012. By August 23, 2012, all data collection activities, site surveys, and reports were complete.

Staff comments

1. This project is also known as the Ethiopian Wind and Solar Energy Development Planning Project. The Chinese project title is 援埃塞俄比亚风电太阳能规划项目 or 埃塞风电太阳能规划报. 2. The system identification number for this project in the Government of Ethiopia’s Aid Management Platform (AMP) is 87143123101134. The AMP records a grant commitment value of ETB 25,466,201 on January 11, 2010. 1 Ethiopian Birr (ETB) was equal to 0.54 Chinese yuan (RMB) in January 2010, which implies that the ETB 25,466,201 grant commitment recorded in the AMP was worth RMB 13,751,748.54 at the time that it was contracted.