Project ID: 70369

CDB Loans USD $50M for Construction of Manzanillo Bay Natural Gas Power Plant (Linked to Project ID#71193)

Pledged amount

$ 54492487.39393384

Adjusted pledged amount

$ 54492487.39393384

Constant 2021 USD

Not recommended for aggregates

This project is not recommended for use in creating aggregated sums. See the documentation for more information about this criteria.

Summary

Funding agency [Type]

China Development Bank (CDB) [State-owned Policy Bank]

Recipient

Dominican Republic

Sector

Energy (Code: 230)

Flow type

Loan

Level of public liability

Central government-guaranteed debt

Infrastructure

Yes

Category

Intent

Mixed (The next section lists the possible statuses.)

Commercial

Development

Representational

Mixed

Financial Flow Classification

OOF-like (The next section lists the possible statuses.)

Official Development Assistance

Other Official Flows

Vague (Official Finance)

Flows categorized based on OECD-DAC guidelines

Project lifecycle

Status

Pipeline: Pledge (The next section lists the possible statuses.)

Pledge

Commitment

Implementation

Completion

Suspended

Cancelled

Milestones

Commitment

2018-01-01

Planned start

2018-07-05

Description

On July 5, 2018 China Huayang Economic and Trade Group Co., Ltd. and the Dominican State Power Company (CDEEE) signed a memorandum of cooperation on the construction of the Manzanillo Natural Gas Power Plant in the Dominican Republic. The title of the project was the Manzanillo Natural Gas Power Plant or '署蒙桑尼尔天然气火力发电厂'. The project will adopt a BOT mode of operation, standing for build operate and transfer, with a 30 year concession. This means that for the next 30 years China Huayang will have control of the plant in a public private concession before transferring full control of the plant to CDEEE once their concessional agreement is over. In exchange for control of the plant, China Huayang will fund the construction of the plant. China Huayang Economic and Trade Group signed the project and the China Development Bank agreed to provide the loans for the project with the Dominican Republic providing a sovereign guarantee for the project. The total value of the loan issued by the China Development Bank was 50 Million USD. This project records the loan portion of the agreement, the 30 year equity stake is recorded in #71193. The power plant includes the construction of a receiving station and shipping terminal, generator set, and a transmission power station, with a production capacity of 1200MW. As of July 14, 2020, the Manzanillo Natural Gas Power Plant project is still under consideration.

Number of official sources

6

Number of total sources

11

Download the dataset

Details

Cofinanced

No

Direct receiving agencies [Type]

Corporación Dominicana de Empresas Eléctricas Estatales (CDEEE) [State-owned Company]

China Huayang Economic and Trade Group Co., Ltd. [Private Sector]

Implementing agencies [Type]

China Huayang Economic and Trade Group Co., Ltd. [Private Sector]

Guarantee provider [Type]

Government of the Dominican Republic [Government Agency]

Loan Details

Bilateral loan

Investment project loan