Chinese government provides $3.6 million grant for Muthurajawela Oil Tank Farm Project (Linked to Record ID#33184)

Commitments (Constant USD, 2023)$8,533,618
Commitment Year2000Country of ActivitySri LankaDirect Recipient Country of IncorporationSri LankaSectorIndustry, Mining, ConstructionFlow TypeGrant

Status

Project lifecycle

Completion

Pipeline: PledgePipeline: CommitmentImplementationCompletion

Timeline

Key dates

Commitment date
Nov 1, 2000
Start (actual)
Jul 1, 2001
End (actual)
May 27, 2004

Geospatial footprint

Map overview

Visualizes the AidData-provided feature geometry for this project.

Loading map…

This project involved an onshore component and an offshore component. The onshore component of the project involved 29 diesel and kerosene storage tanks and all the matching facilities. The offshore component of the project involved a one-point mooring system and a 5.6 km submarine oil transmission pipeline. The Muthurajawela tank farm consists of 21 tanks of 10,000 m3 capacity and 8 tanks of 5,000 m3 capacity. These tanks store and distribute diesel and kerosene. More detailed locational information can be found at https://www.openstreetmap.org/way/316516730

Stakeholders

Organizations involved in projects and activities supported by financial and in-kind transfers from Chinese government and state-owned entities

Funding agencies

Government Agencies

  • Unspecified Chinese Government Institution

Cofinancing agencies

State-owned companies

  • Ceylon Petroleum Corporation

Receiving agencies

Government Agencies

  • Government of Sri Lanka

Implementing agencies

Government Agencies

  • Government of Sri Lanka

State-owned companies

  • China Huanqiu Contracting & Engineering Co., Ltd. (HQCEC)

Loan desecription

Chinese government provides $3.6 million grant for Muthurajawela Oil Tank Farm Project (Linked to Record ID#33184)

Narrative

Full Description

Project narrative

In 2000, the Chinese government provided an additional $3.6 million grant for the Muthurajawela Oil Tank Farm Project. China Eximbank covered 90% of the cost of the $79,528,000 EPC contract value (captured in Record ID#33184). The remaining 10% was funded by Ceylon Petroleum Corporation (CPC). This project involved an onshore component and an offshore component. The onshore component of the project involved 29 diesel and kerosene storage tanks and all the matching facilities. The offshore component of the project involved a one-point mooring system and a 5.6 km submarine oil transmission pipeline. China Huanqiu Contracting & Engineering Corporation — a construction subsidiary of China National Petroleum Corporation specializing in the construction of refineries and chemical fertilizer plants connected to refineries, and mining plants — was the EPC contractor responsible for project implementation. Project implementation began in July 2001 and the Muthurajawela tank farm became operational on May 27, 2004. With the construction of this tank farm, Sri Lanka’s storage capacity for finished petroleum products increased by 250,000 tonnes. Muthurajawela tank farm consists of 21 tanks of 10,000 m3 capacity and 8 tanks of 5,000 m3 capacity. These tanks store and distribute diesel and kerosene. Along with the tanks, CPC installed a new SPBM system, where 60,000 DWT (deadweight tonnage) ships could use the buoy for discharging imported finished products direct from sea to tanks via a submarine pipeline. This terminal includes a loading facility to distribute products by road tankers. However, rail transportation of petroleum products stored in the Muthurajawela tank farm is constrained due to the absence of a railway line. At the time of project completion, a dual pipeline transport systems named the ‘cross country pipeline’ with a length of 6.5 km was expected to link Muthurajawela tank farm with the Supugaskanda facility.