Chinese bank gives China Chengda Engineering Co. $3.26 million USD seller's credit for Caustic Soda Plant Construction Project

Commitments (Constant USD, 2023)$7,525,988
Commitment Year2002Country of ActivitySudanDirect Recipient Country of IncorporationChina (People's Republic of)SectorIndustry, Mining, ConstructionFlow TypeLoan

Status

Project lifecycle

Completion

Pipeline: PledgePipeline: CommitmentImplementationCompletion

Timeline

Key dates

Commitment date
Jan 1, 2002
Start (actual)
Dec 1, 2002
End (actual)
Apr 6, 2004

Geospatial footprint

Map overview

Visualizes the AidData-provided feature geometry for this project.

Loading map…

The purpose of the project is to fund the Caustic Soda Plant Construction Project. More detailed location information can be found at: https://www.openstreetmap.org/relation/3774674

Stakeholders

Organizations involved in projects and activities supported by financial and in-kind transfers from Chinese government and state-owned entities

Ultimate beneficial owners

At least 25% Chinese ownership

Funding agencies

State-owned Commercial Banks

  • Unspecified Chinese State-owned Bank

Receiving agencies

State-owned companies

  • China Chengda Engineering Co. Ltd

Implementing agencies

Government Agencies

  • Sudan Ministry of Industry and Trade

State-owned companies

  • China Chengda Engineering Co. Ltd

Loan desecription

Chinese bank gives China Chengda Engineering Co. $3.26 million USD seller's credit for Caustic Soda Plant Construction Project

Interest typeUnknown

Narrative

Full Description

Project narrative

An unspecified Chinese financial institution provided a $3.26 million USD seller's credit to China Chengda Engineering Co. (中国成达工程有限公司) for the Caustic Soda Plant Construction Project in Sudan. It is unclear when the Chinese bank committed to financing this project. The loan terms are unknown. This project involved constructing a 15 ton daily capacity caustic soda (sodium hydroxide) plant in Gezira State, installing equipment, and providing technical assistance to Sudan's state-owned checmical company under the Ministry of Industry and Trade. China Chengda Engineering Co. LTD was the contractor responsible for implementation. After 16 months of work (starting in December 2002), the plant was put into operation on 6 April 2004.

Staff comments