Skip to content

Overview

Chinese Government provides grant for Third Phase of 8MW Mugere Hydroelectric Power Plant Rehabilitation Project

Commitment Year2001Country of ActivityBurundiDirect Recipient Country of IncorporationBurundiSectorEnergyFlow TypeGrant

Status

Project lifecycle

Completion

Pipeline: PledgePipeline: CommitmentImplementationCompletion

Timeline

Key dates

Commitment date
Jan 1, 2001
Start (actual)
Dec 24, 2000
End (actual)
Sep 7, 2001

Geospatial footprint

Map overview

Visualizes the AidData-provided feature geometry for this project.

Loading map…

The 8MW Mugere Hydroelectric Power Plant is located in Kabezi commune within rural Bujumbura province along the Mugere River. More detailed locational information can be found at https://www.openstreetmap.org/way/150705457

Stakeholders

Organizations involved in projects and activities supported by financial and in-kind transfers from Chinese government and state-owned entities

Funding agencies

Government Agencies

  • Unspecified Chinese Government Institution

Receiving agencies

Government Agencies

  • Government of Burundi

Implementing agencies

Government Agencies

  • Government of Burundi

Loan desecription

Chinese Government provides grant for Third Phase of 8MW Mugere Hydroelectric Power Plant Rehabilitation Project

Narrative

Full Description

Project narrative

In 2000, the Chinese Government provided grant funding to the Government of Burundi for the Third Phase of 8MW Mugere Hydroelectric Power Plant Rehabilitation Project. The monetary size of the grant commitment is unknown. This project was officially completed and handed over to the authorities on September 7, 2001. The 8MW Mugere Hydroelectric Power Plant is located in Kabezi commune within rural Bujumbura province along the Mugere River. Its construction was originally financed by the Chinese Government during the late 1970s and early 1980s. The Chinese Government subsequently funded the First Phase of the 8MW Mugere Hydroelectric Power Plant Rehabilitation Project in 1987 and the Second Phase of the 8MW Mugere Hydroelectric Power Plant Rehabilitation Project in 1993.

Staff comments

The Chinese project title is 布穆杰雷水电站第三次大修项目.