Chinese Government provides grant for Second Phase of the Hydroelectric Power Plant Technical Cooperation Project (Linked to Record ID#73414 and #73416)

Commitment Year2011Country of ActivityBurundiDirect Recipient Country of IncorporationBurundiSectorEnergyFlow TypeGrant

Status

Project lifecycle

Completion

Pipeline: PledgePipeline: CommitmentImplementationCompletion

Timeline

Key dates

Commitment date
Jan 18, 2011

Geospatial footprint

Map overview

Visualizes the AidData-provided feature geometry for this project.

Loading map…

The 1.28 MW Ruvyironza Hydroelectric Power Plant is located in Gitega Province and the 0.85MW Gikonge Hydroelectric Power Plant is located in Muramvya Province. The 8MW Mugere Hydroelectric Power Plant is located in Kabezi commune within rural Bujumbura province along the Mugere River. More detailed locational information can be found at: https://www.openstreetmap.org/node/301351574 and https://www.openstreetmap.org/node/1673541099

Stakeholders

Organizations involved in projects and activities supported by financial and in-kind transfers from Chinese government and state-owned entities

Funding agencies

Government Agencies

  • Unspecified Chinese Government Institution

Receiving agencies

Government Agencies

  • Government of Burundi

Implementing agencies

Government Agencies

  • Government of Burundi

Loan desecription

Chinese Government provides grant for Second Phase of the Hydroelectric Power Plant Technical Cooperation Project (Linked to Record ID#73414 and #73416)

Narrative

Full Description

Project narrative

In 2011, the Chinese Government agreed to provide a grant to the Government of Burundi for the Second Phase of the Hydroelectric Power Plant Technical Cooperation Project. This commitment was codified in letters of exchange that signed by the two governments on On January 11 and 18, 2011. The Second Phase of the Hydroelectric Power Plant Technical Cooperation Project supported the maintenance of three hydroelectric power plants in Burundi: the 8MW Mugere Hydroelectric Power Plant, the 1.28 MW Ruvyironza Hydroelectric Power Plant, and the 0.85MW Gikonge Hydroelectric Power Plant. The first phase of this project was completed in 2008 (see Record ID#73414). It is unknown when the second phase of the project was completed, but it can be assumed that the project did reach completion because the Chinese Government funded a Third Phase of the Hydroelectric Power Plant Technical Cooperation Project in 2015 (see Record ID#73416).