CDB provides $9 million loan for Muxaluando Water Supply System Construction Project (Linked to Record ID#66847 and #65748)

Commitment Year2016Country of ActivityAngolaDirect Recipient Country of IncorporationAngolaSectorWater Supply And SanitationFlow TypeLoan

Status

Project lifecycle

Implementation

Pipeline: PledgePipeline: CommitmentImplementationCompletion

Timeline

Key dates

Commitment date
Jan 1, 2016
Start (actual)
Jun 23, 2016
Last repayment
Dec 29, 2027

Geospatial footprint

Map overview

Visualizes the AidData-provided feature geometry for this project.

Loading map…

The project involved the construction of a new water supply system in the town of Muxaluando within Bengo Province. More detailed locational information can be found at https://www.openstreetmap.org/node/5366016395.

Stakeholders

Organizations involved in projects and activities supported by financial and in-kind transfers from Chinese government and state-owned entities

Ultimate beneficial owners

At least 25% host country ownership

Funding agencies

State-owned Policy Banks

  • China Development Bank (CDB)

Receiving agencies

Government Agencies

  • Government of Angola

Implementing agencies

Government Agencies

  • Government of Angola

State-owned companies

  • Anhui Construction Engineering Group

Loan desecription

CDB provides $9 million loan for Muxaluando Water Supply System Construction Project

Interest typeUnknownMaturity12 years

Narrative

Full Description

Project narrative

On December 9, 2015, China Development Bank (CDB) entered into a $15 billion facility agreement with the Government of Angola (see Record ID#66847). The facility is an oil prepayment facility with repayments being serviced through receivables from a designated oil contract. The facility agreement has a maturity of 12 years and its availability period expired on December 9, 2017. One of the subsidiary loans approved through this facility was a $9 million loan in 2016 for the Muxaluando Water Supply System Construction Project. The proceeds of this loan were used to finance a commercial contract with Anhui Construction Engineering. The project involved the construction of a new water supply system in the town of Muxaluando within Bengo Province. This project entered implementation, but its precise implementation start and end dates are unknown. See Record ID#65748 for other water and energy projects financed through the 2015 CDB facility.

Staff comments

The Portuguese project title is Construção do Novo Sistema de Abastecimento de Água de Muxaluando, na Província do Bengo. The $15 billion facility agreement (captured in Record ID#66847) is fully disbursed.