MOFCOM provides interest-free loan for School of Excellence Construction Project (Linked to Record ID#59593, #66315, #59360, #30165)

Commitment Year2012Country of ActivityDjiboutiDirect Recipient Country of IncorporationDjiboutiSectorEducationFlow TypeLoan

Status

Project lifecycle

Completion

Pipeline: PledgePipeline: CommitmentImplementationCompletion

Timeline

Key dates

Commitment date
Jan 1, 2012
Start (actual)
Jun 6, 2015
End (actual)
Sep 10, 2017
First repayment (originally scheduled)
Dec 29, 2021
Last repayment (originally scheduled)
Dec 27, 2031

Geospatial footprint

Map overview

Visualizes the AidData-provided feature geometry for this project.

Loading map…

More detailed locational information can be found at https://www.google.com/maps/place/School+D'excellence+De+Djibouti/@11.5614892,43.1046745,17z/data=!4m12!1m6!3m5!1s0x162307334e5b5f4f:0xea72f6d6e33c66c6!2sSchool+D'excellence+De+Djibouti!8m2!3d11.561484!4d43.1068632!3m4!1s0x162307334e5b5f4f:0xea72f6d6e33c66c6!8m2!3d11.561484!4d43.1068632 and https://www.openstreetmap.org/way/770660549

Stakeholders

Organizations involved in projects and activities supported by financial and in-kind transfers from Chinese government and state-owned entities

Ultimate beneficial owners

At least 25% host country ownership

Funding agencies

Government Agencies

  • China Ministry of Commerce

Receiving agencies

Government Agencies

  • Government of Djibouti

Implementing agencies

State-owned companies

  • Hunan Provincial Communications Planning Survey & Design Institute

Loan desecription

MOFCOM provides interest-free loan for School of Excellence Construction Project

Grace period10 yearsGrant element75.0516%Interest rate (t₀)0%Interest typeFixed Interest RateMaturity20 years

Narrative

Full Description

Project narrative

Between 2012 and 2014, the Chinese Government signed three different Economic and Technical Cooperation Agreements (ETCAs) with the Government of Djibouti) in order to finance the School of Excellence Construction Project (or Basic Education Project or l’École d’excellence). The first ETCA signed in February 2012 (captured via Record ID#30165) provided an RMB 40 million interest-free loan. The second ETCA signed in January 2013 (captured via Record ID#66315) provided a grant of an unknown value. The third ETCA signed in January 2014 (captured via Record ID#59360) provided a $16.5 million grant. It is unclear how much funding from each ETCA was earmarked for the School of Excellence Project. The Chinese Government reportedly contributed RMB 66 million (about $10.7 million) in total for the School of Excellence Project. The purpose of the project was to construct the School of Excellence, which is located in PK13 district of Djibouti City, about 12 km outside of the capital. Hunan Province Design Institute Co., Ltd was the contractor responsible for project implementation. Construction began on June 16, 2015 and ended on December 15, 2016. The school was opened and put into use on 10 September 10, 2017. A formal project handover ceremony then took place on September 17, 2017. Record ID#85281 captures the loan derived from ETCA #30165. Record ID#59593 records the grant funding derived from ETCAs #66315 and #59360.

Staff comments

1. Since the borrowing terms of the interest-free loan are unavailable, AidData has set maturity to 20 years by default and the grace period to 10 years by default, per China's Foreign Assistance White Paper (http://www.cidca.gov.cn/2018-08/06/c_129925064_3.htm) which states that the maturity of interest-free loans is 20 years, with a drawdown period of 5 years, grace period of 5 years, and repayment over 10 years. AidData treats the drawdown period as providing 5 years of additional grace. 2. The Chinese project title is 援吉布提基础教育学校项目.