[Sino-Congolese Programme] China Eximbank provides $5.33 million loan for construction of 5km ramp connecting the Kalemie stadium to Lumumba Boulevard (Linked to Record ID#450, #59220)

Commitment Year2015Country of ActivityDemocratic Republic of the CongoDirect Recipient Country of IncorporationDemocratic Republic of the CongoSectorTransport And StorageFlow TypeLoan

Status

Project lifecycle

Completion

Pipeline: PledgePipeline: CommitmentImplementationCompletion

Timeline

Key dates

Commitment date
Aug 17, 2015
Start (actual)
Sep 3, 2020
End (planned)
Sep 27, 2022
First repayment
Aug 14, 2025
Last repayment
Aug 10, 2040

Geospatial footprint

Map overview

Visualizes the AidData-provided feature geometry for this project.

Loading map…

This project took place in the province of Tanganyika. More detailed locational information can be found at https://www.openstreetmap.org/directions?engine=fossgis_osrm_car&route=-5.8541%2C29.2450%3B-5.9111%2C29.1919#map=13/-5.8826/29.2185

Stakeholders

Organizations involved in projects and activities supported by financial and in-kind transfers from Chinese government and state-owned entities

Ultimate beneficial owners

At least 25% host country ownershipAt least 25% Chinese ownership

Funding agencies

State-owned Policy Banks

  • Export-Import Bank of China (China Eximbank)

Receiving agencies

Joint Venture/Special Purpose Vehicles

  • Sino-Congolais des Mines (Sicomines SARL)

Implementing agencies

State-owned companies

  • CREC 9

Accountable agencies

Government Agencies

  • Government of Democratic Republic of Congo

Joint Venture/Special Purpose Vehicles

  • Sino-Congolais des Mines (Sicomines SARL)

Guarantors

Government Agencies

  • Government of Democratic Republic of Congo

Collateral providers

Joint Venture/Special Purpose Vehicles

  • Sino-Congolais des Mines (Sicomines SARL)

Loan desecription

[Sino-Congolese Programme] China Eximbank provides $5.33 million loan for construction of 5km ramp connecting the Kalemie stadium to Lumumba Boulevard

Grace period10 yearsGrant element48.1595%Interest rate (t₀)3.839%Interest typeVariable Interest RateLoan tenor6-month rateMaturity25 years

Collateral

Subsidiary (buyer's credit) loan agreements under the master loan (facility) agreement were underpinned by the following source of collateral: the mining rights and titles of SICOMINES SARL, including its rights and titles to the copper and cobalt deposits of Dikuluwe, Mashamba West, Junction D, Cuvette Dima, Cuvette Mashamba and Syncline Dikuluwe Colline D. The borrower was expected to repay the lender with revenues (export receipts) generated by a copper and cobalt mine at Kolwezi (owned by SICOMINES SARL).

Narrative

Full Description

Project narrative

In 2008, China Eximbank issued a $3.003 billion general buyer's credit loan to Sino–Congolais des Mines (Sicomines SARL) — a joint venture — to finance infrastructure projects in the DRC (as captured via Record ID#450). All subsidiary borrowings under the (government-guaranteed) general buyer's credit loan agreement were to be repaid with revenues from mining projects managed by Sicomines SARL. Each subsidiary loan carried a maturity of 25 years, a grace period of 10 years, and an interest rate of 6-month LIBOR plus a 1% margin (or 3.839% at the time of the agreement). All infrastructure projects supported through the general buyer's credit loan were part of the so-called “Sino-Congolese Programme." One of the subsidiary loans issued as part of the 'Sino-Congolese Programme' was a $5,333,019.45 loan for the construction of a 5 km ramp connecting the Kalemie stadium to Lumumba Boulevard. As of 2020, the loan achieved a disbursement rate of 66% ($3,535,947.76 out of $5,333,019.45). CREC 9 — a subsidiary of China Railway Engineering Corporation (CREC) — is the contractor responsible for project implementation. It was awarded a $5,333,019.45 contract (ID#ACGT/DG/07/2019). The project official began construction on September 3, 2020. Asphalting for the ramp began January 28, 2021. The project was completed on September 27, 2022.

Staff comments

1. The French project name is Construction de la bretelle reliant le stade de Kalemie au boulevard Lumumba. 2 According to the 2018 ACGT Annual Report, funding was still pending the approval by the Board of Directors of Sicomines SARL in 2018 after a request was made to reallocate funds from the Kalemie airport terminal project (see Record ID#59220) to this ramp construction project. 3. Given that AidData has captured the entire $3.003 billion China Eximbank loan commitment amount for multiple infrastructure projects via Record ID#450, it does not record a financial commitment (transaction) amount for the subsidiary loan supporting this project to avoid double-counting.