Project ID: 86023

Chinese Government provides RMB 19 million grant for Peace Bridge Renovation Project

Commitment amount

$ 38607032.61987737

Adjusted commitment amount

$ 38607032.62

Constant 2021 USD

Summary

Funding agency [Type]

China Ministry of Commerce [Government Agency]

Recipient

Mongolia

Sector

Transport and storage (Code: 210)

Flow type

Grant

Infrastructure

No

Category

Intent

Development (The next section lists the possible statuses.)

Commercial

Development

Representational

Mixed

Financial Flow Classification

ODA-like (The next section lists the possible statuses.)

Official Development Assistance

Other Official Flows

Vague (Official Finance)

Flows categorized based on OECD-DAC guidelines

Project lifecycle

Status

Completion (The next section lists the possible statuses.)

Pledge

Commitment

Implementation

Completion

Suspended

Cancelled

Milestones

Commitment

2006-04-07

Planned start

2006-05-01

Actual start

2006-05-13

Actual complete

2007-12-21

NOTE: Red circles denote delays between planned and actual dates

Geography

Description

On April 7, 2006, the Chinese Government and the Government of Mongolia signed an RMB 19 million grant agreement for the Peace Bridge Renovation Project. The purpose of the project was to repair a 337 meter bridge that runs from north to south over the Selbe River in Ulaanbaatar’s Khan-Uul district (exact locational coordinates: 47.9076, 106.9129). The bridge was constructed between 1958 and 1963 with a grant from the Chinese Government grant but it eventually fell a state of disrepair and became a safety hazard. In 2005, the Chinese Government dispatched experts to Mongolia to conduct a survey, inspect the bridge, and develop a maintenance plan. The bridge repair project was expected to commence in May 2006. Henan Provincial Communications Planning & Design institute Co., Ltd. was the contractor responsible for implementation. The project was started on May 13, 2006, and completed on December 21, 2007, but its precise implementation start date is unknown. After the completion of the project, local residents complained that the work that was performed was substandard.

Additional details

The Mongolian project title is Энхтайвны гүүр or Энхтайвны гүүрийг засварлаж. The Chinese project title is 蒙古和平桥项目 or 蒙古国和平桥维修加固项目 or 援助蒙古国和平桥维修工程.

Number of official sources

2

Number of total sources

13

Download the dataset

Details

Cofinanced

No

Direct receiving agencies [Type]

Government of Mongolia [Government Agency]

Implementing agencies [Type]

Henan Provincial Communications Planning Survey & Design Institute Co., Ltd. (HPCPSDI) (Henan Transportation Planning and Design Institute Co., Ltd.) [Private Sector]