Sinohydro funds the Masindi Barracks Health Centre IV renovation and expansion in Uganda in 2019

Commitments (Constant USD, 2023)$1,764,579
Commitment Year2019Country of ActivityUgandaDirect Recipient Country of IncorporationUgandaSectorHealthFlow TypeGrant

Status

Project lifecycle

Completion

Pipeline: PledgePipeline: CommitmentImplementationCompletion

Timeline

Key dates

Commitment date
Jan 1, 2019
Start (actual)
Oct 11, 2019
End (planned)
Jun 11, 2020
End (actual)
Apr 16, 2021

Geospatial footprint

Map overview

Visualizes the AidData-provided feature geometry for this project.

Loading map…

The project upgrades the hospital located within the UPDF barracks within Masindi, Uganda. More detailed locational information can be found at https://www.openstreetmap.org/node/1277061228#map=14/1.5287/31.5826

Stakeholders

Organizations involved in projects and activities supported by financial and in-kind transfers from Chinese government and state-owned entities

Funding agencies

State-owned companies

  • Sinohydro Corporation Limited

Receiving agencies

Government Agencies

  • Government of Uganda

Implementing agencies

Private Sector

  • Excel Construction Ltd

Loan description

Sinohydro funds the Masindi Barracks Health Centre IV renovation and expansion in Uganda in 2019

Narrative

Full Description

Project narrative

On October 11, 2019, a groundbreaking ceremony was held for the Masindi Barracks Hospital project donated by China Electric Power Uganda Karuma 812 Joint Venture, which is effectively controlled by Sinohydro (China Water Resources and Hydropower Construction Corporation). The purpose of the project is to expand and transform the existing hospital, including a new operating room, laboratory, doctor's dormitory, nurse's dormitory, canteen, and the renovation and repair of some original buildings. Originally, the project was expected to finish in 8 months, but it was delayed because of the COVID-19 Pandemic. It was originally expected to cost $1.5 million, but eventually it cost $1.7 million. The project was constructed by local company Excel Construction ltd. and was finished on April 16, 2021 under the witness of officials from the Chinese companies and Uganda People's Defense Force (UPDF).

Staff comments

The Masindi Barracks Health Centre IV is also known as Masindi Barracks Military Hospital and 马辛迪军营医院 in Chinese.