Project ID: 88344

Chinese Government provides $28 million grant for Integrated Vocational Training Centre (Cinfotec) Construction and Equipping Project

Commitment amount

$ 31459809.143339902

Adjusted commitment amount

$ 31459809.14

Constant 2021 USD

Summary

Funding agency [Type]

China Ministry of Commerce [Government Agency]

Recipient

Angola

Sector

Education (Code: 110)

Flow type

Grant

Infrastructure

Yes

Category

Intent

Development (The next section lists the possible statuses.)

Commercial

Development

Representational

Mixed

Financial Flow Classification

ODA-like (The next section lists the possible statuses.)

Official Development Assistance

Other Official Flows

Vague (Official Finance)

Flows categorized based on OECD-DAC guidelines

Project lifecycle

Status

Implementation (The next section lists the possible statuses.)

Pledge

Commitment

Implementation

Completion

Suspended

Cancelled

Milestones

Commitment

2019-04-24

Planned start

2020-01-01

Actual start

2021-02-20

NOTE: Red circles denote delays between planned and actual dates

Geography

Description

On April 24, 2019, the Chinese Government and the Government of Angola signed a $28 million grant agreement for the Integrated Vocational Training Centre (Cinfotec) Construction and Equipping Project. The purpose of the project is to construct and equip the Integrated Vocational Training Centre (Cinfotec) outside the city of Huambo in Fátima district and Huambo province. Upon completion, Cinfotec will be owned by Angola’s Ministry of Public Administration, Labor and Social Security (MAPTSS) and it is expected to have have five buildings that will house training and administrative areas, a library, an amphitheater, 6 classrooms, 28 laboratories and 6 workshops. Theoretical and practical classes will be given in the areas of Mechanics and Production, Information Technologies, Meteorology, Electro-medicine, Electricity and Mechatronics. Upon completion, it is expected that the center will be able to accommodate, on average, 1,240 students per day. Zhongding International Construction Group Co., Ltd. is the contractor responsible for implementation. The project was originally scheduled to commence in 2018. However, it did not officially commence until February 20, 2021. As of December 2021, the project had achieved a 55% completion rate.

Additional details

1. The Portuguese project title is Construção e apetrechamento do Centro Integrado de Formação Tecnológica (CINFOTEC). The Chinese project title is 援安哥拉职业技能培训中心项目. 2. One source suggests that the monetary value of the grant commitment was RMB 128 million rather than $28 million. This issue warrants further investigation.

Number of official sources

8

Number of total sources

14

Download the dataset

Details

Cofinanced

No

Direct receiving agencies [Type]

Government of Angola [Government Agency]

Implementing agencies [Type]

Zhongding International Construction Group Co.,Ltd. [State-owned Company]