Chinese Government provides RMB 1.307 billion grant — via a June 2019 ETCA — for Kalai Khumb-Vanj Section of Dushanbe-Kulma Highway Reconstruction Project (Linked to Record ID#90579, #92674, and #72612)

Commitments (Constant USD, 2023)$197,563,215
Commitment Year2019Country of ActivityTajikistanDirect Recipient Country of IncorporationTajikistanSectorTransport And StorageFlow TypeGrant

Status

Project lifecycle

Implementation

Pipeline: PledgePipeline: CommitmentImplementationCompletion

Timeline

Key dates

Commitment date
Jun 15, 2019
Start (actual)
Jun 23, 2022
End (planned)
Dec 31, 2026

Geospatial footprint

Map overview

Visualizes the AidData-provided feature geometry for this project.

Loading map…

The purpose of this project is to link Kalai-Khumb to Vanj and the Rushon district. This 80 km road segment is part of the 96 km Dushanbe-Kulma highway. The project also involves the construction of two tunnels (5.2 km long), 67 spillways of various diameters, 5 protective corridors (490 meters long), 15 bridges (634 meters long), 180 artificial containment walls (21.8 km long), 54 km of protective walls, and 13 open ditches (1.8 km long). As the project has not yet been completed its exact location cannot be determined. Approximate locational information can be found at: https://www.openstreetmap.org/directions?engine=graphhopper_car&route=38.4539%2C70.7918%3B38.2986%2C71.3363

Stakeholders

Organizations involved in projects and activities supported by financial and in-kind transfers from Chinese government and state-owned entities

Funding agencies

Government Agencies

  • China Ministry of Commerce

Receiving agencies

Government Agencies

  • Government of Tajikistan

Loan description

Chinese Government provides RMB 1.307 billion grant — via a June 2019 ETCA — for Kalai Khumb-Vanj Section of Dushanbe-Kulma Highway Reconstruction Project (Linked to Record ID#90579, #92674, and #72612)

Narrative

Full Description

Project narrative

On June 15, 2019, the Chinese Government and the Government of Tajikistan signed an Economic and Technical Cooperation Agreement (ETCA) (as captured via Record ID#90579), in which the Chinese Government which officially committed RMB 2.5 billion ($360 million) of grant funding for various road projects. The Majlisi Namoayndagon (Tajikistan’s lower house of parliament) yesterday ratified the ETCA on October 30, 2019. The Government of Tajikistan subsequently drew RMB 1.307 billion ($186 million) from the ETCA for the Kalai Khumb-Vanj Section of Dushanbe-Kulma Highway Reconstruction Project (as captured via Record ID#88813). Another grant of RMB 800 million was given in October 2021 (as captured via Record ID#92674). The purpose of the project is to link Kalai-Khumb to Vanj and the Rushon district. This 80 km road segment is part of the 96 km Dushanbe-Kulma highway. The project also involves the construction of two tunnels (5.2 km long), 67 spillways of various diameters, 5 protective corridors (490 meters long), 15 bridges (634 meters long), 180 artificial containment walls (21.8 km long), 54 km of protective walls, and 13 open ditches (1.8 km long). China Bridge and Road Corporation (CRBC) is responsible for implementation. Construction for the highway section officially began on June 23, 2022. This project is expected to reach completion on or before 2026.

Staff comments

1. The Government of Tajikistan also drew upon the grant proceeds from the June 15, 2019 ETCA to finance Phase 3 of the Kurgan-Tyube to Kulob Road Rehabilitation Project (captured via Record ID#72612).