Project ID: 89238

Chinese Government provides RMB 92.2 million via March 2017 ETCA for Pohnpei Secondary Road Project

Commitment amount

$ 15727771.29744595

Adjusted commitment amount

$ 15727771.3

Constant 2021 USD

Summary

Funding agency [Type]

China Ministry of Commerce [Government Agency]

Recipient

Micronesia

Sector

Transport and storage (Code: 210)

Flow type

Grant

Infrastructure

Yes

Category

Intent

Development (The next section lists the possible statuses.)

Commercial

Development

Representational

Mixed

Financial Flow Classification

ODA-like (The next section lists the possible statuses.)

Official Development Assistance

Other Official Flows

Vague (Official Finance)

Flows categorized based on OECD-DAC guidelines

Project lifecycle

Status

Completion (The next section lists the possible statuses.)

Pledge

Commitment

Implementation

Completion

Suspended

Cancelled

Milestones

Commitment

2017-03-27

Actual start

2019-06-26

Planned complete

2020-12-26

Actual complete

2021-09-07

NOTE: Red circles denote delays between planned and actual dates

Geography

Description

On March 27, 2017, China’s Ministry of Commerce (MOFCOM) and Government of Micronesia signed an economic and technical cooperation agreement (ETCA), which committed RMB 92,229,500 of grant funding for unspecified projects. Then, on January 15, 2018 and January 30, 2018, the two sides signed an exchange of letters, allocating all of the grant funds to the Secondary Road Project in Pohnpei State. The purpose of this project was to reconstruct six existing roads equal to 8,708 meters in Madolenihmw within Pohnpei State: Lukop, Metipw, Dolopwail, Kepine, Areu Pah, and Areu Powe. China Railway 14th Bureau Group Co., Ltd. was the contractor responsible for project implementation. A consortium consisting of CCCC Highway Planning and Design Institute Co., Ltd. and Beijing CCCC Highway and Bridge Engineering Supervision Co., Ltd. was responsible for project management. A groundbreaking ceremony took place on June 26, 2019 and the project was originally expected to reach completion within 18 months (December 26, 2020). The project was ultimately completed and handed over to the local authorities on September 7, 2021. David W. Panuelo, President of the Federated States of Micronesia, attended the completion ceremony in Madolenihmw Municipality and described the Pohnpei Secondary Road Project as the latest example of how 32 years of the FSM-China Great Friendship had resulted in tangible and visible benefits for FSM citizens. Going President Panuelo were Huang Zheng, CHina’s ambassador to the FSM; Esmond B. Moses, vice speaker of the 22nd FSM Congress; Reed B. Oliver, governor of Pohnpei State; Stevick Edwin, speaker of 10th Pohnpei State Legislature; and John A. Adolph, traditional leader or Iso Nahnken of Madolenihmw.

Additional details

1. This project is also known as the Pohnpei Secondary Road Construction Project. The Chinese project title is 援密克罗尼西亚波纳佩州二级公路项目 or 密克罗尼西亚波纳佩州二级公路项目.

Number of official sources

5

Number of total sources

10

Download the dataset

Details

Cofinanced

No

Direct receiving agencies [Type]

Government of Micronesia, Federated States of [Government Agency]

Implementing agencies [Type]

China Railway 14th Bureau Group Co., Ltd. (CRCC14) [State-owned Company]

CCCC Highway Planning and Design Institute Co., Ltd. [State-owned Company]

Beijing CCCC Highway and Bridge Engineering Supervision Co., Ltd. [State-owned Company]