Skip to content

Overview

CMEC provides $15 million bridge loan for 15MW Lusiwasi Upper Hydropower Project

Commitments (Constant USD, 2023)$15,094,444
Commitment Year2018Country of ActivityZambiaDirect Recipient Country of IncorporationZambiaSectorEnergyFlow TypeLoan

Status

Project lifecycle

Completion

Pipeline: PledgePipeline: CommitmentImplementationCompletion

Timeline

Key dates

Commitment date
May 31, 2018
End (actual)
Feb 10, 2021
Last repayment (originally scheduled)
Nov 29, 2019

Geospatial footprint

Map overview

Visualizes the AidData-provided feature geometry for this project.

Loading map…

The purpose of the project is to construct a 15MW run-of river hydropower plant — with three 5MW power generation units — that is located about 700 km from Lusaka, and is about 5 km upstream of the existing 12MW Lusiwasi Hydropower Station. A canal which conveys the water towards the units is approximately 4.5 km up to the Forebay from the canal intake. More detailed locational information can be found at https://www.openstreetmap.org/node/8937581249 and https://www.openstreetmap.org/relation/12900317

Stakeholders

Organizations involved in projects and activities supported by financial and in-kind transfers from Chinese government and state-owned entities

Ultimate beneficial owners

At least 25% host country ownership

Funding agencies

State-owned companies

  • China Machinery Engineering Corporation (CMEC)

Receiving agencies

State-owned companies

  • Zambia Electricity Supply Corp. (ZESCO)

Implementing agencies

State-owned companies

  • China Machinery Engineering Corporation (CMEC)

Loan description

CMEC provides $15 million bridge loan for 15MW Lusiwasi Upper Hydropower Project

Grant element2.6075%Interest rate (t₀)6%Interest typeFixed Interest RateMaturity1.5 years

Narrative

Full Description

Project narrative

On May 31, 2018, China Machinery Engineering Corporation (CMEC) and Zambia Electricity Supply Corporation (ZESCO) Limited — Zambia’s state-owned power company — signed a $15 million supplier’s credit (bridge loan) agreement for the 15MW Lusiwasi Upper Hydropower Project. The loan carries the following borrowing terms: a maturity of 1.5 years from when the major funding comes through, an a 6% interest rate. It amount outstanding was The loan’s amount outstanding was $14,780,000 as of December 31, 2018, $14,780,000 as of December 31, 2019, $14,780,000 as of December 31, 2020, $17,041,704 (inclusive of $2,260,563 in interest arrears) as of June 30, 2021 and $6,897,015 as of June 30, 2022. The purpose of the project is to construct a 15MW run-of river hydropower plant — with three 5MW power generation units — that is located about 700 km from Lusaka, and is about 5 km upstream of the existing 12MW Lusiwasi Hydropower Station. A canal which conveys the water towards the units is approximately 4.5 km up to the Forebay from the canal intake. CMEC is the contractor responsible for implementation. On February 14, 2020, the first of the three 5MW power generation units went into operation. By February 10, 2021, all three power generation units were in operation.

Staff comments

1. This project is also known as the Lusiwasi Upper Hydropower, 15MW - Bridging Finance Project. 2. The tenure of the loan is 18 months (1.5 years) from when the loan comes into effect to when the major financing for the project comes through. It is unclear when and whether the major financing loan has been committed. Hence, AidData estimates the maturity as 1.5 years. This issue warrants more investigation.