Chinese Engineering Coy rehabilitates airfield in Greenville

Commitment Year2015Country of ActivityLiberiaDirect Recipient Country of IncorporationLiberiaSectorGovernment And Civil SocietyFlow TypeGrant

Status

Project lifecycle

Completion

Pipeline: PledgePipeline: CommitmentImplementationCompletion

Timeline

Key dates

Commitment date
Jan 1, 2015
Start (actual)
Mar 10, 2015
End (actual)
Apr 5, 2015

Stakeholders

Organizations involved in projects and activities supported by financial and in-kind transfers from Chinese government and state-owned entities

Funding agencies

Government Agencies

  • Chinese Contingent of United Nations Mission to Liberia (UNMIL)

Receiving agencies

Government Agencies

  • Government of Liberia

Implementing agencies

Government Agencies

  • Chinese Engineering Coy (CHINENGR-17)

Loan description

Chinese Engineering Coy rehabilitates airfield in Greenville

Narrative

Full Description

Project narrative

From March 10, 2015, to April 5, 2015, the Chinese Engineering Coy (CHINENGR-17), part of the United Nations Mission in Liberia, conducted rehabilitation works at the airfield of the coastal town of Greenville. CHINENGR-17 cleared vegetation on the 1.4 km runway before compacting the surface. The group also constructed 84 drainage outlets, each about two meters wide. Four parking lots spanning 200 square meters were also rehabilitated, as well as some 120 square meters of the bumpy ground around the airfield's fuel station. The rehabilitation works were estimated to last two months, but CHINENGR-17 finished in 4 weeks. The Chinese FPU-3 compatriots stationed in Greenville also provided support.