Chinese Government provides grant for Miguel Hilario Alcívar Hospital Reconstruction Project via two ETCAs (Linked to Record ID#59063, #59712)

Commitments (Constant USD, 2023)$28,658,890
Commitment Year2017Country of ActivityEcuadorDirect Recipient Country of IncorporationEcuadorSectorReconstruction Relief And RehabilitationFlow TypeGrant

Status

Project lifecycle

Implementation

Pipeline: PledgePipeline: CommitmentImplementationCompletion

Timeline

Key dates

Commitment date
Oct 11, 2017
Start (actual)
Aug 19, 2019
End (planned)
Feb 25, 2022

Geospatial footprint

Map overview

Visualizes the AidData-provided feature geometry for this project.

Loading map…

The project helped reconstruct the Miguel Hilario Alcívar Hospital. More detailed locational information can be found at https://www.openstreetmap.org/way/413026317

Stakeholders

Organizations involved in projects and activities supported by financial and in-kind transfers from Chinese government and state-owned entities

Funding agencies

Government Agencies

  • China Ministry of Commerce

Receiving agencies

Government Agencies

  • Government of Ecuador

Implementing agencies

Government Agencies

  • Ecuador Work Contracting Service (SECOB)

Private Sector

  • Castro y Castro Constructora Cia. Ltda.
  • RHR Rock & Hydro Resources

Loan description

Chinese Government provides grant for Miguel Hilario Alcívar Hospital Reconstruction Project via two ETCAs (Linked to Record ID#59063, #59712)

Narrative

Full Description

Project narrative

On October 20, 2016, the Chinese Government signed a Memorandum of Understanding (MOU) pledging to fund and implement the Miguel Hilario Alcívar Hospital Reconstruction Project in Bahía de Caráquez for the Government of Ecuador. The China Ministry of Commerce subsequently signed two economic and technical cooperation agreements (ETCA) which allocated grant funding covering the total cost of this hospital project. The first is an RMB 300 million grant signed on October 11, 2017 (see Record ID#59712), and the second is an RMB 200 million grant signed on December 12, 2018 (see Record ID#59063). It is unclear how much from these grants were allocated to the Bahía Hospital Reconstruction Project. The purpose of this project is to reconstruct a hospital in Bahía de Caráquez following an April 2016 earthquake. Works Contracting Service (Servicio de Contratación de Obras, SECOB) is the organization in charge of project implementation for Ecuador, per the October 2016 MOU. The government organization approved a technical contract with the Bahía Consortium (comprised of Castro & Castro Constructora and RHR Rock & Hydro Resources) to carry out the work on or about August 19, 2019 worth USD 26,931,848 (listed as about 29 million USD in 2022, see "Gobierno le promete a Manabí que el 2022 tres hospitales estarán listos" and "Hospital de Bahía de Caráquez será una realidad"). The total budget exceeded USD 44.3 million as of August 19, 2019, though with supplemental contracts the total project cost has likely increased. Construction for the hospital began in 2019 and was intended to be completed by February 25, 2022. In April 2021, a supplementary contract was signed for the construction of three additional units not included in the original contract. As of July 16, 2022, while the project continued to face delays, it was said to be about 90% complete.

Staff comments

1. Transaction amount is based on the original contract for three reasons: (1) it is reported by a Recipient Official Source, rather than a media source, (2) it is a more precise number, and (3) it is the more conservative number. While the actual transaction amount is in RMB because the project is funded via ETCA, the amount from each ETCA and the amount in RMB is unknown/no agreement document has been found specifying the RMB amount. 2. This project is also called the Bay Hospital Project or Proyecto del Hospital de Bahía.