Narrative
Full Description
Project narrative
On July 2, 2019, the Chinese Government and the Government of Kenya signed a $39.2 million (KES 3,500,000,000) grant agreement for the Ministry of Foreign Affairs Headquarters Construction Project. The purpose of this project is to construct a new headquarters for the Kenyan Ministry of Foreign Affairs in Nairobi. According to the Government of Kenya’s Electronic Project Management Information System (e-ProMIS), this project was originally scheduled to commence on July 1, 2020 and conclude on June 30, 2023. However, as of May 14, 2021, construction had not yet begun.
Staff comments
1. The Government of Kenya’s reference code for this project is mofa0012020. The e-ProMIS ID number for this project is 2020/058257.c