Project ID: 95460

Chinese Government provides TOP $ 5.5 million grant for Nuku'alofa Sidewalk Project

Commitment amount

$ 2695461.8978773667

Adjusted commitment amount

$ 2695461.9

Constant 2021 USD

Summary

Funding agency [Type]

Dongguan Municipal Government [Government Agency]

Recipient

Tonga

Sector

Other social infrastructure and services (Code: 160)

Flow type

Grant

Infrastructure

Yes

Category

Intent

Development (The next section lists the possible statuses.)

Commercial

Development

Representational

Mixed

Financial Flow Classification

ODA-like (The next section lists the possible statuses.)

Official Development Assistance

Other Official Flows

Vague (Official Finance)

Flows categorized based on OECD-DAC guidelines

Project lifecycle

Status

Completion (The next section lists the possible statuses.)

Pledge

Commitment

Implementation

Completion

Suspended

Cancelled

Milestones

Commitment

2018-01-01

Actual start

2018-07-25

Planned complete

2020-12-31

Actual complete

2022-11-27

NOTE: Red circles denote delays between planned and actual dates

Geography

Description

In 2018, Dongguan City from China’s Guangdong Province provided a grant worth approximately TOP $ 5.5 million to the Government of Tonga for the Nuku'alofa Sidewalk Project. The purpose of the project was to construct a 30 km dual way sidewalk in Nuku’alofa. The project officially commenced on July 25, 2018. it was originally expected to reach completion by the end of 2020. However, it was ultimately completed on November 27, 2022.

Additional details

1. This project is also known as the Pedestrian Pathway Project. The Chinese project title is 汤加人行步道项目. 2. Some sources suggest that the grant commitment was worth TOP $13 million rather than TOP $5.5 million. This issue warrants further investigation.

Number of official sources

5

Number of total sources

7