Project ID: 95783

Chinese Government provides grant for Phase 3 of the Araniko Highway Long-Term Maintenance Project (Linked to Project ID#43970 and #52936)

Summary

Funding agency [Type]

China Ministry of Commerce [Government Agency]

Recipient

Nepal

Sector

Transport and storage (Code: 210)

Flow type

Grant

Infrastructure

Yes

Category

Intent

Development (The next section lists the possible statuses.)

Commercial

Development

Representational

Mixed

Financial Flow Classification

ODA-like (The next section lists the possible statuses.)

Official Development Assistance

Other Official Flows

Vague (Official Finance)

Flows categorized based on OECD-DAC guidelines

Project lifecycle

Status

Completion (The next section lists the possible statuses.)

Pledge

Commitment

Implementation

Completion

Suspended

Cancelled

Milestones

Commitment

2019-10-13

Actual start

2020-12-31

Actual complete

2022-03-26

Geography

Description

The 114 km Araniko highway, which runs from Kathmandu to Tatopani in Sindhupalchok district, was damaged in five different places by an earthquake that took place on April 25, 2015. The Chinese Government subsequently committed grant funding equivalent to 760 million Nepali rupees for Phase 1 of the Araniko Highway Long-Term Maintenance Project. China Railway 14th Construction Bureau started construction on August 8, 2016, and handed over the highway after repairing it on March 3, 2017. Then, in June 2018, the Chinese Government and the Government of Nepal signed letters of exchange, which committed additional grant funding for Phase 2 of the Araniko Highway Long-Term Maintenance Project. China Railway 14th Bureau Group was responsible for Phase 2 implementation. This phase of the project was completed in July 2020. On October 13, 2019, the Chinese Government and the Government of Nepal signed letters of exchange, which committed additional grant funding for Phase 3 of the Araniko Highway Long-Term Maintenance Project. China Railway 14th Bureau Group was responsible for Phase 3 implementation and Henan Communications Planning & Design Institute Co., Ltd. was responsible for Phase 3 design. On-site project design and survey work commenced on December 31, 2020. Phase 3 was officially completed and handed over to the Government of Nepal on March 26, 2022.

Additional details

1. The Chinese project title is 尼泊尔阿尼哥公路三期保通项目 or 援尼泊尔阿尼哥公路保通项目.

Number of official sources

6

Number of total sources

13

Download the dataset

Details

Cofinanced

No

Direct receiving agencies [Type]

Government of Nepal [Government Agency]

Implementing agencies [Type]

China Railway 14th Bureau Group Co., Ltd. (CRCC14) [State-owned Company]

Henan Communications Planning & Design Institute Co., Ltd. [State-owned Company]