Project ID: 97299

Chinese government provides AUD $4.54 million for the Fit for Purpose Landing Craft for the Line and Phoenix Group project in Kiribati

Commitment amount

$ 3413533.834586466

Adjusted commitment amount

$ 3413533.83

Constant 2021 USD

Summary

Funding agency [Type]

Unspecified Chinese Government Institution [Government Agency]

Recipient

Kiribati

Sector

Transport and storage (Code: 210)

Flow type

Grant

Infrastructure

No

Category

Intent

Development (The next section lists the possible statuses.)

Commercial

Development

Representational

Mixed

Financial Flow Classification

ODA-like (The next section lists the possible statuses.)

Official Development Assistance

Other Official Flows

Vague (Official Finance)

Flows categorized based on OECD-DAC guidelines

Project lifecycle

Status

Implementation (The next section lists the possible statuses.)

Pledge

Commitment

Implementation

Completion

Suspended

Cancelled

Milestones

Commitment

2021-11-30

Actual start

2022-08-15

Planned complete

2023-05-01

Geography

Description

In the Kiribati Ministry of Information, Communication, Transport, and Tourism Development & State-Owned Enterprise's Strategic Plan for 2021-2024, the purchase of a fit-for purpose landing craft to service the Line & Phoenix Groups was listed a goal, with an estimated price tag of USD 2,000,000. Then, in the government of Kiribati's 2022 Development Budget, presented on November 30th, 2021 it was stated that China will provide USD 2.4 million for the Fit for Purpose Landing Craft for the Line and Phoenix Group project. On August 15th, 2022, the Kiribati National Fishing Line released photos from the contact signing ceremony. The value of the 39 meter landing craft was stated to be AUD 4.54 million. The construction of the craft will be done by Zhoushan Ningshing Ship Building and Repairing Co., Ltd. Construction began after the signing of the contract and is expected to take ten months, with a projected end date of May 2023. The finished vessel will be delivered to Kiribati National Shipping Line from China to Tarawa in June 2023. The landing craft will have a carrying capacity of 100 passengers and 180 tonnes of cargo. The Line Islands and the Phoenix Islands are two island groups that are part of Kiribati's outer islands. The development of these islands is managed by the Ministry for Line and Phoenix Islands Development (MLPID or Linnix)

Number of official sources

4

Number of total sources

4

Download the dataset

Details

Cofinanced

No

Direct receiving agencies [Type]

Government of Kiribati [Government Agency]

Implementing agencies [Type]

Zhoushan Ningshing Ship Building and Repairing, Co., Ltd [Private Sector]

Kiribati National Shipping Line (KNSL) [Government Agency]