Project ID: 974

China Eximbank provides RMB 337 million government concessional loan for 15MW Mekin Hydropower Project

Commitment amount

$ 69337081.7109825

Adjusted commitment amount

$ 69337081.71

Constant 2021 USD

Summary

Funding agency [Type]

Export-Import Bank of China (China Eximbank) [State-owned Policy Bank]

Recipient

Cameroon

Sector

Energy (Code: 230)

Flow type

Loan

Level of public liability

Central government debt

Financial distress

Yes

Infrastructure

Yes

Category

Intent

Development (The next section lists the possible statuses.)

Commercial

Development

Representational

Mixed

Financial Flow Classification

ODA-like (The next section lists the possible statuses.)

Official Development Assistance

Other Official Flows

Vague (Official Finance)

Flows categorized based on OECD-DAC guidelines

Project lifecycle

Status

Completion (The next section lists the possible statuses.)

Pledge

Commitment

Implementation

Completion

Suspended

Cancelled

Milestones

Commitment

2010-01-07

Planned start

2009-03-01

Actual start

2010-07-01

Actual complete

2015-12-23

NOTE: Red circles denote delays between planned and actual dates

Geography

Description

On November 5, 2009, the Chinese Government and the Government of Cameroon signed a preferential loan framework agreement for the 15MW Mekin Hydropower Project. Then, on January 7, 2010, China Eximbank and the Ministry of Economy, Planning and Regional Development of the Republic of Cameroon signed a government concessional loan (GCL) loan agreement [CHINA EXIMBANK GCL NO. (2009) 45 TOTAL NO. (295) LOAN SERIAL NO. 1290003052009110688] worth RMB 337 million for the 15MW Mekin Hydropower Project. The GCL carries the following borrowing terms: a 20-year maturity, a 4 year grace period, a 2% interest rate, a 0% default (penalty) interest rate, a 0.30% management fee, and a 0.30% commitment fee. The borrower was expected to use the proceeds of the loan to finance a commercial (EPC) contract [ID# 000478/MINEE/CAB] between the Government of Cameroon's Ministry of Energy and Water Resources and China National Electric Equipment Corporation (CNEEC), which was signed on March 16, 2009. As of December 31, 2020, the loan (GCL) had achieved a 98.4% disbursement rate and its outstanding amount was equivalent to CFA 16.1 billion. The project involved the construction of a rockfill dam, a 105-million cubic meters reservoir, a 15 MW power plant (with three, 5MW power generators), a 6.3/110KV interconnection substation in Mekin, a 110/30KV interconnection substation at Ndjom Yekombo, and a 110/30kV high-voltage transmission line from Mekin to Ndjom Yekombo (connected to the southern power grid). The dam and power plant are located in arrondissement of Meyomessala and electricity is evacuated to the eight districts of the Dja and Lobo Division, South Region. China National Electric Equipment Corporation was the EPC contractor responsible for project implementation. The Cameroonian Government also established a state-owned company -- called Hydro Mekin (or Hydromekin) -- to oversee implementation of the project. Project implementation commenced November 2011 and it was completed on December 23, 2015. However, after the facility was powered up in June 2019, it experienced technical difficulties. The facility was put back into production in May 2021 and it currently supplies the D31 Sangmélima and D32 Meyomessala feeders. There are some indications that the China Eximbank loan for the 15MW Mekin Hydropower Project may have financially underperformed vis-a-vis the original expectations of the lender. In January 2019, Cameroon unilaterally withheld debt service payments to China Eximbank. The lender responded by withholding new loan disbursements. Then, in July 2019, China Eximbank and the Government of Cameroon signed a debt rescheduling agreement (as captured via Project ID#88213). Under the terms of the agreement, China Eximbank agreed to reschedule 18 loans previously contracted by the Government of Cameroon — with scheduled principal repayments between July 2019 and March 2022 — by allowing the borrower to defer scheduled principal repayments between July 2019 and March 2022 to later dates but without any maturity extensions. The total amount of restructured debt was equivalent CFA 148 billion ($253 million) — or 70% of the loan principal that was scheduled for repayment between July 2019 and March 2022. Under the terms of the agreement, the Government of Cameroon agreed to repay 30% of the loan principal according to the original July 2019-March 2022 schedule (i.e. without any payment deferrals). The lender and the borrower also agreed to cancel the committed but undisbursed loan balances worth approximately CFA 10 billion (for certain loans with disbursement deadlines that had already passed). Then, in January 2020, the International Monetary Fund (IMF) classified the Government Cameroon as facing a high risk of debt distress. Eighteen months later, during an address before Cameroon’s National Assembly on June 28, 2021, the Minister of Water and Energy (MINEE) Gaston Eloundou Esommba provided an update on the ICBC-financed Bini à Warak Hydroelectric Power Plant Project. He noted that the project had been 'on hold' since November 2019 because ICBC suspended the loan agreement, even though the Government of Cameroon had already mobilized XAF 22 billion of counterpart funding. He also explained that 'the reason for this suspension is that Cameroon did not settle some of its debts towards China on time, so, it is in a cross-default situation.’

Additional details

1. The Chinese project title is 默坎水电站项目现. The French project title is Projet de Construction de la centrale hydroéléctrique de Mekim sur le Dja or Centrale hydroélectrique de Mékin. 2. The China Eximbank loan agreement can be accessed in its entirety via SourceID#67429 or https://www.documentcloud.org/documents/20485533-cmr_2010_168. 3. The project ID number for this transaction in Cameroon's Development Assistance Database (DAD) is CAM/000708. 4. The 110/30kV high-voltage transmission line was originally designed as a 63kV high-voltage transmission line. 5. One official source (https://www.dropbox.com/s/a400557jut579m5/Government%20of%20Cameroon%202020%20Register%20of%20Chinese%20Loans%20and%20Borrowing%20Terms.pdf?dl=0) identifies the face value of the loan as RMB 301,169,855 and the loan commitment date as March 21, 2010.

Number of official sources

27

Number of total sources

38

Download the dataset

Details

Cofinanced

No

Direct receiving agencies [Type]

Cameroon Ministry of Economy, Planning, and Regional Development (MINEPAT) [Government Agency]

Implementing agencies [Type]

China National Electric Engineering Co., Ltd. (CNEEC) [State-owned Company]

Hydro Mekin [State-owned Company]

Cameroon Ministry of Water, Resources, and Energy [Government Agency]

Loan Details

Maturity

20 years

Interest rate

2.0%

Grace period

4 years

Grant element (OECD Grant-Equiv)

37.7805%

Bilateral loan

Government Concessional Loan

Investment project loan